Andacollo Hypogene Project ?Overview Project description: Sulphide copper concentrator Throughput:55,000 tpd Location: Approximately 50 km from La Serena Elevation: Approximately 1,000 m ASL Start feasibility study: July 2005 Start of construction: May 2007 Construction completion: December 2009 Final cost(1,2,3):435 Million US $ (1) Excludes third party costs, 220 kV power line (2) Cost is based on a Chilean Peso to US Dollar foreign exchange rate of 535 to 1 (3) Does not include US$40.3 million for the Elqui River Pipeline Project or US$8.0 million for the stock pile cover