Avoiding Karst by Getting Under It - Jefferson Barracks Tunnel, St. Louis

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 8
- File Size:
- 1111 KB
- Publication Date:
- Jan 1, 2016
Abstract
"INTRODUCTION The Jefferson Barracks Tunnel is in the final stages of design and is expected to go out to bid in the summer of 2016. The project is located in south St. Louis County along the west bank of the Mississippi River, about 13 km downstream of the St. Louis Gateway Arch. The project consists of a deep sanitary sewer tunnel, a deep pump station and several intakes. The intakes will divert sanitary flows into the tunnel and the tunnel will convey the flows by gravity to the Lemay No. 3 Pump Station, which will pump them up into the Lemay Waste Water Treatment Plant. The tunnel is about 5.4 km long and will be lined with 84-inch (2.1 m) fiberglass pipe. It drops at a gradient of 0.1 percent from south to north and will be bored through strong limestone using a hard-rock tunnel boring machine (TBM). The diameter of the TBM is anticipated to be about 3.4 m. The Owner’s original concept was for a relatively shallow tunnel so as to minimize construction and pumping costs. The preferred alignment ran close to the river, next to the existing force main, which was to be abandoned. Keeping the tunnel close to the force main would reduce the amount of shallow sewer work needed to connect the existing feeder sewers to the new tunnel. Several geotechnical investigations were performed, with shallowly focused geophysics and the borings all going exactly down the conceptual tunnel depth. Limestone bluffs run along the Missouri side of the river. These bluffs are pockmarked by sinkholes and riddled with karst. Large, well-known caves occur both north and south of the alignment. Karst features, including deep crevices and possible caves, were found in those early geotechnical investigations. Many of these features extended well below the level of the Mississippi River and would have been encountered by the tunnel. If a large crevice or cave were encountered, then the inflow of mud and water into the tunnel could have been large and possibly uncontrollable. Something had to be done to mitigate this situation. Pre-excavation grouting was considered, but the program would have been huge and extremely expensive. Using a closed-face TBM with bolted and gasketed lining was also considered, but that too was both risky and extremely expensive. The Owner could have abandoned the tunnel altogether and built a new force main, but that would have brought a whole new set of problems and was undesirable to the Owner. The last option was to move the tunnel away from the karst."
Citation
APA:
(2016) Avoiding Karst by Getting Under It - Jefferson Barracks Tunnel, St. LouisMLA: Avoiding Karst by Getting Under It - Jefferson Barracks Tunnel, St. Louis. Society for Mining, Metallurgy & Exploration, 2016.