Case study of a hoisting facility upgrading

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 3
- File Size:
- 2462 KB
- Publication Date:
- Jan 1, 1991
Abstract
"Within six months from award of a project management contract, Les Mines Dumagami Limitée, Cadillac, Quebec, was operating its new hoisting facility. This was accomplished with less than a six-week shutdown of mine production while still maintaining shaft access for underground maintenance.The work involved installing a refurbished /3.5 ft diameter double drum hoist, replacing a timber headframe with a newsteel headframe, increasing the ore bin capacity from 500tons to 1000 tons, constructing a new substation, and upgrading related facilities.This paper describes the work and methods used by various contractors, Les Mines Dumagami Limitée and J.S. Redpath Mining Consultants Limited to bring this project to a successful completion. It discusses the history of the project from proposal stage through to the design, procurement, scheduling, and construction management. The paper also comments on problems that were encountered and the methods used to overcome them.IntroductionThe Donald J. Laronde Mine of Les Mines Dumagami Limitée (Dumagarni), a gold and copper producer, is located in northwestern Quebec, approximately half way between Val d'Or and Rouyn. The mine started production in the spring of 1988 and the first gold bar was poured in June 1988.Following a request by Dumagami, on February 22, 1989, J.S. Redpath Mining Consultants Limited(Redpath) delivered a proposal to increase hoisting capabilities from 1500 tpd to a minimum of 2500tpd. Although various concepts were considered, Redpath proposed a new hoist house along the same shaft axis as the existing hoist, and located on the site of the existing substation. They would then provide a new substation, replace the headframe with a largersteel structure , gain extra storage capacities by increasing the bin heights, and raising the roof of the bin house accordingly.Although underground mining would have to be stopped for a month, the mill production would be maintained by feed from Dumagami's open pit.Figure 1 shows the original plant layout and Figure 2 represents the general arrangement after the project was completed . Table 1 compares the original hoisting facilities to the new facilities.On March 2, Dumagami awarded Redpath a contract that included preliminary engineering, detailed engineering, procurement and contract administration, and later added construction management. The preliminary engineering refined the initialconcept, selected major equipment, and prepared schedules and capital cost estimates for the total project."
Citation
APA:
(1991) Case study of a hoisting facility upgradingMLA: Case study of a hoisting facility upgrading. Canadian Institute of Mining, Metallurgy and Petroleum, 1991.