Chuquicamata Sulphide Plant: Crushing Section

The American Institute of Mining, Metallurgical, and Petroleum Engineers
A. P. Svenningsen
Organization:
The American Institute of Mining, Metallurgical, and Petroleum Engineers
Pages:
4
File Size:
387 KB
Publication Date:
Jan 1, 1952

Abstract

IN the early stages of design it was not considered necessary that separate crushing plants be built for the new sulphide concentrator and smelter until sometime in the future. The plan was to use the existing crushing facilities for both oxide and sulphide ore. A few additions were contemplated for the existing plants, such as increased bin capacity, and possibly two new secondary crushing units. The more the problem was studied and discussed with the plant operators, the more it became evident that it was complex. It involved the classification of different kinds of ore from the open pit mine -sulphide, oxide and mixed-and how best to separate them so that each kind of ore was given the proper processing and treatment. It also involved the problem of keeping the different ores from being contaminated in bins, hoppers and chutes. Added to these, transportation became complicated and would involve additional handling and loading of ore from crushing plants to conveyors, to bins, and finally to railroad cars which were to be hauled to the concentrator and dumped into the fine ore bin. General In the early part of 1951 it was decided that the concentrator be constructed with ten grinding units instead of seven as originally authorized. The smelter was to be increased proportionally and naturally also the overall tonnages of ore to be handled by the new sulphide plant. Due to this increase in plant capacity and the larger tonnages involved, the difficulties which would arise by using the existing crushing plants were increased to a point where it became evident that the building of new crushing plants for sulphide ore exclusively was technically, as well as economically, advantageous. Authorization was, therefore, given by the company to construct new crushing plants to handle 30,000 tons of ore per day, and capable of reducing the run-of-open-pit ore to the proper size feed for the 10x14-ft rod mills in the concentrator. The ore, mined in the open pit, sometimes comes in pieces as large as 6 to 7 ft diam. The rod mills may call for ore crushed to 3/4 in. The large .size of ore delivered from the open pit determined that a 60-in. gyratory crusher be used as primary breaker. Such a crusher will have a capacity considerably in excess of 30,000 tons per day. The crusher will be a single discharge unit driven by a 500-hp electric motor through a tear coupling and a floating shaft. This type of drive has proven successful at a number of other crusher installations which our company has operating in the United States, Mexico and South America. The tear coupling will protect both the crusher and motor against damage in case of overload. No new features are incorporated in the design of the crusher itself, except that the, discharge chute is made the full width of the crusher with parallel sides instead of the usual converging sides. This change in detail should eliminate, a feature which has been a bottleneck in some of the operating plants and has caused loss of production due to ore hanging up and blocking the chute. The secondary crushing plants will have three 7-ft standard Symons cone crushers and six 7-ft short head Symons crushers. Between the primary and secondary crushing plants a coarse ore bin will be constructed with a nominal draw-off capacity of 30,000 tons of ore. The standard Symons and the short head Symons will be in separate buildings. All the crushing plants and the coarse ore bin are interconnected with conveyor belts for transporting the ore to the crushers at the tonnage rate desired. The final product of the new crushing plants is produced by the short head crushers. It will be delivered onto a conveyor belt leading to the top of the fines ore bin in the concentrator. A separate conveyor belt running the full length of the fines ore bin and provided with a movable tripper of rugged design will discharge the sulphide ore into the bin. The concentrator bin is planned and designed so that the installation of this additional conveyor will not interfere with the operation of the two railroad tracks on which crushed ore is brought from the existing oxide plant. Thus when completed the bin can be filled simultaneously by ore from the new crushing plant and by ore from the existing leaching plant.
Citation

APA: A. P. Svenningsen  (1952)  Chuquicamata Sulphide Plant: Crushing Section

MLA: A. P. Svenningsen Chuquicamata Sulphide Plant: Crushing Section. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1952.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account