Coal - Computer Method for Estimating Proper Machinery Mass for Stripping Overburden (MINING ENGINEERING, 1961, vol. 13, No. 5, p. 480)

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 8
- File Size:
- 2089 KB
- Publication Date:
- Jan 1, 1961
Abstract
The author demonstrates an approach for analyzing overcasting requirements for a stripping project. This approach to the problem employs indicated trends in the relationship of the weight of the machine (only electropowered draglines are considered) to its ability to do stripping work. Strip mining in the domestic coal industry is contributing a greater proportion of overall production than at any time in the past. U.S. Bureau of Mines statistics show that the percentage of total production mined in 1958 by stripping methods increased to more than 30 pct, up from 22 pct in 1951. The tendency to favor strip and open pit mining exists in other mining activities, but such trends are not as clearly outlined as in the coal industry. Significantly, the depth of overburden in coal properties considered suitable for stripping is also increasing. A depth of 50 to 60 ft of overburden was once considered to be about the maximum amount that could be handled economically. Today, a depth of 80 to 100 ft is frequently taken into consideration for simple overcasting operations (i.e., excavating overburden and dumping it in the spoil position where it remains indefinitely). Accompanying these changes, there have been continuing studies searching for procedures to appraise deeper stripping problems. Although the only known practicable way to accurately evaluate a proposed stripping venture is to make studies (including cost estimates) step by step, it is nevertheless desirable to have a quick method for making preliminary evaluations of potential strip mining operations. A recently devised digital computer method of providing a preliminary simple overcasting analysis for a stripping prospect relates the indicated trends in the relationship of the weight of the machine to its ability to do stripping work. In addition, this approach employs situations where the geometry of each cut-and-spoil section is assumed to take certain defined relationships for varying overburden depths. Slopes are necessarily considered to be stable, which means such practical factors as the mechanics of soils are neglected for the sake of convenience. Definition of Terms: Photographs A and B show a shovel-type and a dragline-type of simple overcast operation, plus terms used to denote certain parts of a pit. Pits that follow a straight line when projected on a horizontal plane are referred to as straightaway. It has been assumed that all section drawings accompanying this article pertain to straightaway cuts which, in turn, means that areas can be compared by relative volume. The volume of overburden is measured in virgin cubic yards. Material displaced from its virgin state to a spoil area normally occupies a larger volume than when in situ; the difference is termed swell, and it is expressed as a percentage of the original volume. For example, if the original cut volume is denoted V cu yd, and the spoil volume is 1.2 V cu yd, the swell is a positive 20 pct. MAXIMUM USEFULNESS FACTOR (MUF) CONCEPT Men experienced in overburden removal give emphasis to the weight of the machine in relation to its value as an excavator. From the writer's understanding, value has been only loosely defined and discussed generally and vaguely. The concept is considered important, however, since it is based upon the observations of many men. It provides a clue for the approach taken to solve deep stripping problems. In the procedure described below, value has been arbitrarily established as the product of the nominal dipper size of the shovel (or dragline) times a functional dumping reach. MUFs—Shovel: A shovel's capability to handle thick overburden is usually limited by its ability to dispose of the spoil. Thus the dumping reach, as well as its dumping height, is significant. The angle of repose of spoil material must also be considered. Although such slope angles vary among different mines, jobs, and materials, a slope of 1.25 to 1, frequently found in both planning and practice, is used by this author in the illustration of this analytical method. The relationship of the shovel's geometry to a stripping operation is shown in Fig. 1. To gain maximum advantage in constructing spoil piles, the shovel is placed so that its tracks adjacent to the spoil are as close as possible to the rib of the coal deposit. A vertical plane passing through the line
Citation
APA:
(1961) Coal - Computer Method for Estimating Proper Machinery Mass for Stripping Overburden (MINING ENGINEERING, 1961, vol. 13, No. 5, p. 480)MLA: Coal - Computer Method for Estimating Proper Machinery Mass for Stripping Overburden (MINING ENGINEERING, 1961, vol. 13, No. 5, p. 480). The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1961.