Commissioning And Ramp Up Of The Hpgr Circuit at Newmont Boddington Gold

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 23
- File Size:
- 1090 KB
- Publication Date:
- Jan 1, 2012
Abstract
In September 2009, Newmont began the commissioning of a 3 stage crushing and milling circuit at its Boddington Gold Operation in Western Australia. The Boddington ore has been recognized as one of the hardest and most abrasive ores treated to date and this played a pivotal role in the selection of crushing and HPGR technology for this operation as opposed to the more conventional SABC circuit. This paper will examine the scale up from laboratory to pilot plant and full scale operation of the crushing circuit. There have been many challenges to overcome in the first 18 months of operation; however, the HPGRs have in general met design expectations and performance is expected to improve further with ongoing design changes
Citation
APA:
(2012) Commissioning And Ramp Up Of The Hpgr Circuit at Newmont Boddington GoldMLA: Commissioning And Ramp Up Of The Hpgr Circuit at Newmont Boddington Gold. Canadian Institute of Mining, Metallurgy and Petroleum, 2012.