Construction Up Raises with TH perforation
- Organization:
- International Society of Explosives Engineers
- Pages:
- 10
- File Size:
- 926 KB
- Publication Date:
- Jan 26, 2026
Abstract
Currently, mining operations seek to be competitive in the market. To achieve this, one of the relevant factors is to maintain and improve the productivity of the extractive processes, mainly the loading from the point of opening of the mineral bodies. To do this, many techniques suggest reducing production costs, with the first opening of your free-face up raises.
However, there are different ways to carry out these open-face raises up opening processes, where the balance of costs and construction time must be well planned to meet production plans. Operationally, there are different techniques for its construction, the most common being Blind-Hole up Raises and those with drilling with current production equipment that operates mining operations.
This study shows a methodology and the results of the implementation of access stack drilling with production drilling rigs for a maximum height of 15 m with electronic detonators in production blasting.
Within the methodology used, Qa/Qc processes were considered in cargoes with explosives, instrumentation for monitoring (vibrations), VOD registration, among others.
As a result, of a total of 12 raises up blasts, construction time was reduced by 45% and the cost of drilling and blasting (P&V) was reduced by 50%, for up raises with a maximum height of 15 meters. Regarding the efficiency of the heights, this was 97% compared to the planned drilling design.
Citation
APA: (2026) Construction Up Raises with TH perforation
MLA: Construction Up Raises with TH perforation. International Society of Explosives Engineers, 2026.