Construction — You need risk-based cost estimating

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 8
- File Size:
- 6551 KB
- Publication Date:
- Apr 1, 2016
Abstract
"Estimating and managing the costs of complex infrastructure projects – in the planning/design and construction phases, for both owners and contractors – has been a challenge for decades. The more complex and technologically advanced the project, the greater the uncertainty, including potential risks that are important to owners and contractors, such as:• Cost risks to owners – meeting budget and schedule, maintaining public credibility.• Cost risks to contractors – profit, consequences of loss, impacts to reputation/future work.This concern has been addressed in various ways by the underground construction industry for some time (Reilly, 2001). In particular, while significant advances have been made in cost estimating for the planning and design phases (Reilly et al., 2004), that are important to agencies and political decision-makers, it is not apparent that these advances have been widely adopted for construction cost estimates. The reasons for this may relate to lowbid considerations – any method that tends to increase the contractor’s cost estimate, by including risk or likely costs, could lead to an erosion of the contractor’s competitive position – if others are not similarly required to include such costs.Different cost estimating methods produce different levels of information. Specifically, there is a large difference in the character and depth of information if a deterministic (quantities times price plus a contingency) and risk-based cost methods are used. It is this difference in character and depth of information that is the reason that risk-based cost estimating has potential value for owners and contractors. Figure 1 presents hypothetical cost results from deterministic and risk-based methods and illustrates some of these differences.In Fig. 1, the results for deterministic and risk-based cost estimates are given related to the potential profit or loss for a typical project. As is evident in this example, there is significant potential for costs to be realized that are higher than the proposal/bid value estimated using a deterministic approach, with a 15 percent probability of a loss. There is a 30 percent probability that the project will have a reduced profit. There is a 55 percent probability that the project will return a good profit. Using a risk-based approach, it is possible to better recognize this potential outcome in the bid phase and, as a consequence, develop a strategy to:"
Citation
APA:
(2016) Construction — You need risk-based cost estimatingMLA: Construction — You need risk-based cost estimating. Society for Mining, Metallurgy & Exploration, 2016.