Deep shaft hoisting at LaRonde —The Penna shaft hoisting plant

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 7
- File Size:
- 250 KB
- Publication Date:
- Jan 1, 2004
Abstract
Agnico-Eagle started sinking the Penna Shaft in 1995 with a hoisting plant capable of hoisting 1800 t/d from a 2240 m deep shaft. Exploration success led to the installation of a hoisting plant capable of extracting 4500 t of ore and 1800 t of waste per day from a depth of 2210 m. The introduction of a new rope selection factor, permitting a safety factor of 4.0, represented the breakthrough required for a cost-effective project. This paper describes the process taken to introduce the new rope selection factor and its impact on the original plant.
Citation
APA:
(2004) Deep shaft hoisting at LaRonde —The Penna shaft hoisting plantMLA: Deep shaft hoisting at LaRonde —The Penna shaft hoisting plant . Canadian Institute of Mining, Metallurgy and Petroleum, 2004.