Degerstrom’s large heap leoch operation profitably mines low-grade gold

Society for Mining, Metallurgy & Exploration
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
1
File Size:
174 KB
Publication Date:
Jan 1, 1986

Abstract

In 1981, North American Degerstrom Contracting began gold mining on the Little Rocky Mountain Range, near Zortman, MT. In the past four years, the price of gold has fluctuated from a high of $16/g ($500 per oz) to a low of $9.60/g ($300 per oz). With that kind of a moving target, profitability presents a management challenge. Based in Spokane, WA, Degerstrom employs 85 people at the mine. It is one of the largest heap leach operations in the nation. Last year, 8 Mt (9 million st) of low-grade ore was moved to the leach pads in a two-shift, five-day operation. The current pit being worked produces 218 kt/m (240,000 stpm) of leaching ore. Ore fragmentation critical The gold bearing ore has no defined patterns or seams. It is an igneous intrusion resulting from volcanic activity. It occurs spontaneously throughout the range. To recover the gold, areas are staked out and core samples are taken and analyzed. These data determine if the ore is rich enough to mine. Once mining begins, an average of 150 holes are drilled and blasted on a two-day rotation. Five Ingersoll-Rand T4s drill on a 4- x 4.5-m (14- x 15-ft) spacing to a 7.6-m (25-ft) depth. "When we first came to this site, we drilled on a 3.6- x 3.6-m (12- x 12-ft) pattern," said Paul Baker, superintendent for N.A. Degerstrom Contracting. "We did some experimenting using a high density emulsion in the bottom of the hole and filling the rest with regular Anfo." The high density emulsion saved the company on overall drilling and blasting costs since the holes could be spaced on a wider pattern and still achieve the high degree of fragmentation needed for leaching. Blasting is important because the gold lays in the natural strata of the rock. Also, the ore is not crushed before it goes to the leach pads. So complete fragmentation is critical. Terrain dictates loading/hauling system The shot ore is worked in 6 m (20 ft) benches by two Caterpillar 245 front shovels equipped with 3 m3 (4 cu yd) buckets, a 992C wheel loader with a 12.6-m3 (16.5-cu yd) bucket, and a 988E high lift fed by a D9H. A Caterpillar D10 tractor trap dozes to the loader. According to Baker, the 6 m (20 ft) bench is an efficient lift for the front shovel and the wheel loader. In tight quarters or in a pocket of ore, Degerstrom uses the 245s. For high production areas, the wheel loader is used. The hauling fleet includes 28 Cat 773 off highway trucks. The 45 t (50 st) trucks are seven pass loaded by the 245s with a 25-second cycle time per bucket load. The 992C loads the trucks in two passes in less than 30 seconds. The cycle time is four to five minutes for a 1.2-km (4000-ft) haul on grades that average 10%. Grades, in some places, exceed 16%. "We use the 773s because they have a low weight-to-horsepower ratio - that's what you need in steep country," Baker said. The trucks haul the shot ore to the leach pad. Currently, Degerstrom is working a pad that has a capacity for 5 Mt (5.5 million st) of ore. Building the leach pads The base of the pads resemble a large drainage basin. They take about one month to construct. A 0.3-m (1-ft) layer of impervious bentonite clay is hauled in and leveled by a Cat D9H tractor. A 30-mm (1.2-in.) PVC liner is then laid in place on top of the clay base. It, in turn, is covered with tailings from an old on-site mill. Degerstrom uses the tailings to protect the liner from tears when the ore is dumped. The ore is leveled and built up in 9 m (30 ft) lifts by the D9H. The tractor rips the top layer. Then, a network of plastic irrigation pipe is put in place to distribute a cyanide solution over the surface. The leaching solution percolates through the ore and dissolves the gold. The solution drains from the pads and is pumped to a 22.7-ML (6-million gal) pregnant solution holding pond. The liquid then goes through two separate filtration units. One unit removes entrained solids and the other side adds a zinc dust to precipitate the gold. This is collected on filters. The affluent then returns to a solution holding pond for redistribution through the pipeline network. Typically, 80% of the pad's potential recovery takes place in the first 30 days of leaching. The process stops when the ambient temperature falls below the cyanide's freezing level. And each pad has a leach cycle of four to five years before recovery values decline to a point where further leaching becomes uneconomical. At Zortman, it takes 9 t (10 st) of ore to produce 31 g (1 oz) of gold. It is therefore critical to keep total production costs down and efficiency high.
Citation

APA:  (1986)  Degerstrom’s large heap leoch operation profitably mines low-grade gold

MLA: Degerstrom’s large heap leoch operation profitably mines low-grade gold. Society for Mining, Metallurgy & Exploration, 1986.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account