Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot Plant
    
    - Organization:
 - The Australasian Institute of Mining and Metallurgy
 - Pages:
 - 7
 - File Size:
 - 266 KB
 - Publication Date:
 - Jan 1, 1984
 
Abstract
Aberfoyle Limited operated a matte  fuming pilot plant, incorporating a  SIROSMELT furnace in 1980/81. This plant  was a significant advance in both smelting  and tin extraction technology. Important  design, construction and commissioning  aspects are discussed and some of the key  points to emerge from this phase of the  work are reviewed.
Citation
APA: (1984) Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot Plant
MLA: Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot Plant. The Australasian Institute of Mining and Metallurgy, 1984.