Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot Plant

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 7
- File Size:
- 266 KB
- Publication Date:
- Jan 1, 1984
Abstract
Aberfoyle Limited operated a matte fuming pilot plant, incorporating a SIROSMELT furnace in 1980/81. This plant was a significant advance in both smelting and tin extraction technology. Important design, construction and commissioning aspects are discussed and some of the key points to emerge from this phase of the work are reviewed.
Citation
APA:
(1984) Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot PlantMLA: Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot Plant. The Australasian Institute of Mining and Metallurgy, 1984.