Design, Construction and Commissioning of the Ridgeway Concentrator Regrind Circuit at NewcrestÆs Cadia Valley Operations

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 8
- File Size:
- 678 KB
- Publication Date:
- Jan 1, 2005
Abstract
In July 2004 a flotation concentrate regrind circuit was commissioned in the æHigh GradeÆ Ridgeway concentrator at NewcrestÆs Cadia Valley Operations. This was the culmination of two years of project testing, process design and planning which commenced shortly after commissioning the concentrator in March 2002. During the two-year project evolution alternative grinding technologies were evaluated from conventional ball milling through to sand milling. A Detritor mill was eventually selected for the duty and the criteria on which this selection was based will be presented. As the project evolved so too did the equipment sizing with the concentrator quickly exceeding design capacity of 4 Mtpa and currently averaging 5.6 Mtpa, the process design had to accommodate this and future potential throughput increases. This paper will focus on the supporting testwork, circuit surveys and concentrate properties which were used as the design basis for the project. The economic evaluation which led to the project receiving board approval in November 2003 will also be presented. Detailed design and construction management issues will be discussed as will preliminary results and findings up to November 2004.
Citation
APA:
(2005) Design, Construction and Commissioning of the Ridgeway Concentrator Regrind Circuit at NewcrestÆs Cadia Valley OperationsMLA: Design, Construction and Commissioning of the Ridgeway Concentrator Regrind Circuit at NewcrestÆs Cadia Valley Operations. The Australasian Institute of Mining and Metallurgy, 2005.