Electrical Installations At The Miami Mine

The American Institute of Mining, Metallurgical, and Petroleum Engineers
C. A. Ross B. R. Coil
Organization:
The American Institute of Mining, Metallurgical, and Petroleum Engineers
Pages:
4
File Size:
647 KB
Publication Date:
Jan 1, 1952

Abstract

NEW demands for underground power in the Miami mine of the Miami Copper Co., Miami, Ariz. has brought about expansion of the distribution system for both ac and dc power. Progress in mining equipment and the normal changes in the mine were responsible for this increased demand. Early power requirements were for pumping and haulage. A 440 v ac power line down No. 5 shaft took care of a small pumping load and shaft station lighting, 275 v dc power was generated by motor generator sets on the surface, with a churn drill hole from surface to the 570 haulage level serving as a cableway. Electric lights were installed where power was available, and thus were confined to the haulage level and shaft stations. All industrial power in the Miami area is 25-cycle, which dates back to the hydroelectric generator installation at Roosevelt Dam in 1908-10. The Problem The main haulage level was moved to the 720 level and later, to the 1000 level, requiring a longer feeder line with the resultant voltage drop. Also, as mining progressed to the east, the churn drill hole for the power cable would have been subjected to subsidence cracks. The first extension in the use of electricity was in electric blasting. About 1935 the mine went to electric blasting, using the dc haulage current. Bringing electric current to the working levels of the mine for blasting greatly expanded the use of electric lights. Lights were used in tool rooms, powder and cap magazines, stairways, and other semi-permanent installations. Like all mines, Miami Copper began to study and experiment with mechanical mucking and transportation of ore by slushers, shakers, and belts during the late 1930's and early 1940's. At the beginning of the program, power was supplied from the haulage level 275 v dc system. Later it became necessary to run a cable, carrying 440 v ac power, down the No. 7 ventilation shaft. The increased use of power came about gradually, and many new problems were added, not the least being the introduction of switch boards and power cables into the working areas of the mine, where drifts and crosscuts take weight, and require repairs. The 25-cycle current presented special problems, in that 25-cycle transformers are twice as large and about 2V2 times as heavy as 60-cycle transformers of the same power output. The 25-cycle transformers were considered too large for installation in the mining areas. In 1947 the distribution system was revised and standards were adopted, governed by the following
Citation

APA: C. A. Ross B. R. Coil  (1952)  Electrical Installations At The Miami Mine

MLA: C. A. Ross B. R. Coil Electrical Installations At The Miami Mine. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1952.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account