Extractive Metallurgy Division - Canadian Copper Refiners Ltd. Electric Furnace Melting Practice

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 6
- File Size:
- 610 KB
- Publication Date:
- Jan 1, 1956
Abstract
Electric furnace installation and tough-pitch copper-casting operation at Canadian Copper Refiners Ltd. are described. General layout, power supply and control, refractories, induction pour hearth, casting equipment, metal temperature control, and oxygen-content control are discussed. E LECTRIC furnace at Canadian Copper Refiners Ltd. was put into operation in August 1949. The installation was designed primarily to melt electrolytic copper cathodes and to produce vertically cast tough-pitch shapes. To meet emergencies during reverberatory furnace shut-downs, provision was made for casting horizontal tough-pitch wire bars. Due to the ease with which metal temperatures, melting rates, oxygen content, and casting hours can be altered to suit production demands, the electric furnace has met the requirements admirably. General Layout The plant has been described by H. S. McKnight' and by J. H. Schloen and E. M. Elkin.2 Since these papers were written, the electric furnace has been installed in a 140 ft extension of the original casting building. The extension, 264 ft in width, is divided into one 24 ft and four 60 ft bays, each a continuation of similar bays in the older building. Fig. l, a partial floor plan of the extension, shows the location of major equipment. Power Supply and Control Power for the electric furnace and its auxiliary equipment is delivered by Quebec Hydro over two 12 kv three-phase, 60 cycle pole lines. One line is in use, while the second serves as an emergency standby. Connections for the electric furnace from these lines, which also feed the refinery power house, are made to a substation on Canadian Copper Refiners Ltd. property. Connections between this substation and the furnace transformer room are in underground conduit. The are-furnace transformer, 550 v auxiliary-equipment transformer, and 12 kv switchgear are in the transformer room near the furnace. Stepdown from 12 kv to are-furnace voltages is done by a 7500 kva oil-immersed water-cooled three-phase 60 cycle transformer. This unusually high kva rating is available because the arc furnace and transformer were adapted from a steel-melting unit. Secondary voltages are available in 16 steps between 251 and 95 v (across phases). A four-position tap changer, operated from the furnace switchboard is connected to taps yielding 199, 164.5, 127, and 115 v, respectively. The transformer primary feeder is equipped with a General Electric Magne-Blast circuit breaker. The pour hearth, casting wheel, bosh conveyor, and other auxiliary equipment are fed by a 12 kv to 550 v, 750 kva three-phase 60 cycle transformer. Graphite electrodes, 14 in., with tapered nipples are held in the are-furnace electrode arms with steel wedges. The arms, fed from the transformer secondary busbars by flexible cable bundles, are actuated by winch cables. Direct-current motors operating the winches are supplied by a 250 v motor-generator set. Power input to the furnace is controlled from the furnace switchboard. The board has the usual combination of remote controls for the 12 kv breaker and transformer tap changer, meters, overload relays, automatic and manual electrode motion controls, switchgear, etc. When power is on the furnace, automatic electrode feed is used; the power draw on a given voltage tap then is governed by current-limiting rheostats. The rheostats work through a Westinghouse bal-lanced-beam control circuit which, in turn, operates reversing contactors in the winch motor circuits. Arc Furnace The arc furnace is a standard-type NT Pittsburgh 'Lectromelt with inside shell diameter 12 ft 3¾ in. By hydraulic-lift cylinders, the furnace can be tilted forward to 39 ½ ° and backward to 5" from horizontal. A roof-swing cylinder is also installed but not used. Fig. 2 shows refractory-lining details. With the lining as shown, operating life between repairs is 6 to 9 months of two-shift casting operation. Charge slot, skim door, and roof refractories then are replaced completely, and any necessary repairs made to side walls. Bottom life is longer and the original under courses are still in service, while the top course was replaced in October 1951. The launder is lined with high chrome-magnesite trough brick backed by fireclay and insulating brick. The trough is covered with fireclay brick and asbestos sheet. At intervals, openings 12x6 in. are left in the permanent covering. These are covered with
Citation
APA:
(1956) Extractive Metallurgy Division - Canadian Copper Refiners Ltd. Electric Furnace Melting PracticeMLA: Extractive Metallurgy Division - Canadian Copper Refiners Ltd. Electric Furnace Melting Practice. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1956.