Fast-Track Construction At Mount Polley

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 5
- File Size:
- 554 KB
- Publication Date:
- Jan 1, 1998
Abstract
In June 1997, Mount Polley Mining Corp., a division of Imperial Metals Corp., completed an 18-kt/d (20,000 stpd) gold-copper mine in central British Columbia. Fast-track construction and extensive off-site construction were combined with an aggressive project schedule to build the mine in one year. This was three months ahead of schedule and 7% below the original budgeted cost of C$123.5 million (US$86 million). The Mount Polley Mine was the first of a crop of new open-pit mines in British Columbia. The Mount Polley deposit has been explored since the mid-1960s when it was known as the Cariboo Bell property. From 1988, Imperial Metals completed drilling and metallurgical testing on the deposit. This led to a positive feasibility study and the issuing of a Mine Development Certificate in 1991. The project was later shelved due to falling metals prices and the strength of the Canadian dollar. In late 1994, Imperial merged with Bethlehem Resources Corp., bringing a strong project team to the company. The deposit was then re-evaluated, ore reserves revised and additional metallurgical testing was performed. The result was a revised project plan. It indi¬cated that a financially feasible gold-copper mining op¬eration could be constructed at Mount Polley operat¬ing at 18 kt/d (20,000 stpd). In May 1996, an agreement was reached with Sumitomo to jointly fund and develop the project. By early 1996, final plans and permits were being prepared for construction, scheduled to begin in June 1.996. On-site work commenced on May 28th, 1996 following lifting of the road restrictions. Mount Polley Mining acted as its own project manager. Construction was completed in June 1997. Plant runup took place in July and full production began in August. Through the use of off-site construction and the careful selection of contractors who cooperated to complete some 12 major contracts, it was possible to reduce the mine and mill construction time from 16 to 13 months. Off-site construction for all possible aspects of the work and the use of used milling equipment allowed significant savings in overall capital costs of construction. Total costs for the mine, mill and tailings dam equated to C$6,100/t/d of throughput. The mill design incorporates several innovative features that will aid maintenance and allow flexibility of operation. The operation is designed as a closed system and meets the latest environmental standards. Concentrate is shipped by truck to the port of Vancouver. Revenues for the mine come from the mine's production of about 3.1 t/a (100,000 oz/year) of gold and 10.8 kt/a (24 million lbs/year) of copper during the first four years of the 12-year mine life.
Citation
APA:
(1998) Fast-Track Construction At Mount PolleyMLA: Fast-Track Construction At Mount Polley. Society for Mining, Metallurgy & Exploration, 1998.