Final Tunnel Liner At The Mill Creek 3 Project

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 4
- File Size:
- 3696 KB
- Publication Date:
- Jan 1, 2008
Abstract
The 6-m- (20-ft-) diameter cast-in-place tunnel lining for Phase 3 of the Mill Creek Tunnel (MCT3) has been completed. This article summarizes aspects of liner design and ad-dresses the construction approach in placing the liner in areas of tunnel that experienced crown overbreak. Tunnel lining production rates, installation procedures and form buoyancies experienced during concrete placement will also be presented. The Mill Creek Phase 3 tunnel (MCT-3) is expected to be completed this year. It is one of the largest tunneling projects undertaken by the Northeast Ohio Regional Sewer District (NEORSD) to date. The tunnel horizon is situated within the Devonian Chagrin Shale rock formation at an average depth of 85 m (280 ft). The tunnel was excavated using a two-pass method. A full face, fully shielded, Robbins 7.2-m- (23.8-ft-) diameter tunnel boring machine (TBM) was used to excavate approximately 4,500 m (15,000 ft) of tunnel and facilitate installation of initial supports (first pass). The final lining (second pass) consists of 305-mm- (12-in.-) thick cast-in-place reinforced concrete and integral low flow channel. Seven shafts were constructed on the project. The excavation of the tunnel commenced at Shaft 14 and proceeded down grade to Shaft 9, the terminus shaft. Because of the presence of overbreak in the tunnel crown, measures were required to support the form and counteract the effects of buoyancy during concrete placement.
Citation
APA:
(2008) Final Tunnel Liner At The Mill Creek 3 ProjectMLA: Final Tunnel Liner At The Mill Creek 3 Project. Society for Mining, Metallurgy & Exploration, 2008.