FMC Paradise Peak -An Update (ef21eb80-7a2b-45ba-8a64-ebdae013a670)

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 8
- File Size:
- 584 KB
- Publication Date:
- Jan 1, 1988
Abstract
FMC's Paradise Peak Mine was discovered in July 1983. The deposit at discovery contained 11,340 ,000 tonnes (12,500,000 tons) of ore grading 3.71 glt (0.108 oz/ton) Au and 120 glt (3.5 oz/ton) Ag. A feasibility study was completed by Davy McKee in May 1984, with detailed engineering starting in June 1984. Construction of the facility started on January 2, 1985 with plant start-up taking place on April 14, 1986, two and one half months ahead of schedule and more than 10% under budget. This paper describes the status of the operation approximately 1-1/2 years after start-up including revisions and additions to equipment and process.
Citation
APA:
(1988) FMC Paradise Peak -An Update (ef21eb80-7a2b-45ba-8a64-ebdae013a670)MLA: FMC Paradise Peak -An Update (ef21eb80-7a2b-45ba-8a64-ebdae013a670). Society for Mining, Metallurgy & Exploration, 1988.