Four Metre Diameter Raise Drilling at Olympic Dam Project S.A.

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 10
- File Size:
- 895 KB
- Publication Date:
- Jan 1, 1988
Abstract
In the first half of 1987 two four metre diameter raise bore holes were drilled at the Olympic Dam Project for ventilation purposes. The first hole, 476 m x 4.0 m diameter was completed in 96 days, 35 days longer than scheduled. The second hole, 407 m x 4.0 m diameter was completed in 39 days, 2 days ahead of schedule. Both holes were drilled with a Robbins 121R rig using a Wirth head that consisted of 23 face cutters and 5 side cutters, supplied by a contractor. After the sites were located a grouting program was carried out to help seal off an aquifer between 160 and 180 m below the surface. Cavities discovered in the Andamooka Limestone were filled with concrete. Because of the overlying dune sands and clay both sites were pre-sunk to the competent Andamooka Limestone.
Citation
APA: (1988) Four Metre Diameter Raise Drilling at Olympic Dam Project S.A.
MLA: Four Metre Diameter Raise Drilling at Olympic Dam Project S.A.. The Australasian Institute of Mining and Metallurgy, 1988.