General Design Sulphide Ore Plant

The American Institute of Mining, Metallurgical, and Petroleum Engineers
Wilbur Jurden
Organization:
The American Institute of Mining, Metallurgical, and Petroleum Engineers
Pages:
3
File Size:
384 KB
Publication Date:
Jan 1, 1952

Abstract

THE writer's first experience with a nonferrous reduction plant of great magnitude was at the Washoe reduction works of Anaconda some 35 years ago. Here was a plant which had been planned with remarkable skill and foresight considering the time and the state of development of copper-plant practice in the year 1902. The designer utilized topography to fullest extent to provide proper sequence of operations and, what is most remarkable, to leave adequate space for future developments, most of which at that time were unknown. However, the practice then was to locate the various units of the reduction works at the most advantageous points of the existing terrain with little regard for tramming or other auxiliaries and then connect these various units by the essential trackage, conveyor systems, piping, etc., as the need developed. This occasionally led to undesirable track arrangements, sharp curves, and steep grades, especially when it became necessary to extend various portions of the plant. Conveyor systems also became rather complicated, running as they did at various angles, and such items as piping and electrical distribution were often found to be in the wrong place, entirely inadequate in size, or awkwardly arranged for any kind of extension. This condition was not peculiar to Anaconda, for all copper plants at that time were built in the same manner and it was the constant association with these difficulties which, in the year 1925, influenced the layout of the Andes Copper Mining Co. plant. In that plant all trackage was laid out straight and level, all conveyors at right angles to each other with minimum length and number of transfers. All buildings were placed parallel and the main structures were complete for all purposes so that auxiliary buildings and dog houses would not be added later. Piping and electrical work was provided for in the original layout and carefully designed to avoid additions and alterations, and careful study given to every movement of material throughout the entire plant so that it would be accomplished with the least possible effort. Naturally it was hardly expected to attain all these objectives perfectly but our efforts did succeed in creating a plant which was unique and outstanding for its time-1927. It was also most gratifying to find that these design principles contributed to considerable savings starting right in the drafting room, carrying through the construction and ultimately yielding savings in operations and manpower. Not only that, but such a plant gives the observer an impression of symmetry and order, is more attractive to the workmen, and unquestionably eliminates many accident hazards. However, the Andes plant buildings were fitted to the existing terrain instead of having terrain created to fit the buildings-an item which we found advantageous to correct on the next large plant. At Morenci in 1939, all of the desirable features of the Andes plant such as parallel buildings, etc., were incorporated; but we went one step further-power shovels were brought in to make the terrain fit the reduction works. The result at Morenci is well-known and needs no elaboration here, but the success achieved by the design methods used for this and previous plants naturally influenced and guided the layout of the Chuquicamata sulphide plant which is the largest yet conceived. Chuquicamata Plant Design At Chuquicamata several factors not encountered previously complicated the problem to a great extent. The most desirable location for the smelter would allow smelter gases to blow directly into the open-pit mine already producing 60,000 tons of oxide ore per day and employing 1550 men. This, of course, would be a serious condition and, therefore, we were forced to move the smelter to a less desirable location but followed our previous experience at Morenci and made the terrain fit the job. The most difficult problem, however, was the provision for receiving various types of ore both by rail and conveyor. These consisted of: 1-Sulphide-bearing residue from the stockpile from which oxide copper had previously been leached. 2-Sulphide-bearing residue coming direct from the leaching vats. 3-Sulphide ore crushed at the existing crushing plants and hauled to the concentrator in cars. 4-Sulphide ore from the new crushing plant adjacent to the concentrator. 5-Sulphide ore obtained
Citation

APA: Wilbur Jurden  (1952)  General Design Sulphide Ore Plant

MLA: Wilbur Jurden General Design Sulphide Ore Plant. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1952.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account