Gold Recovery At Gold Fields - Chimney Creek

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 10
- File Size:
- 391 KB
- Publication Date:
- Jan 1, 1989
Abstract
Gold Fields Mining Corporation started processing ore from it's Chimney Creek operation in northern Nevada in November, 1987. Since that time production has averaged about 200,000 ounces per year from the milling and dump leaching circuits combined. The events that led up to commissioning of the plant started in January of 1985 when the Gold Fields exploration team drilled their first hole in an area now known as Discovery Hill. The major orebody was located later in the year in what is currently the major focus of activity, the North Pit. Subsequent drilling since plant startup has found another 14 million tons of ore two miles south of the original orebody. This South Pit orebody is currently being stripped and metallurgical testing is underway. Engineering Engineering on the Chimney Creek plant started in earnest in May, 1986. Davy McKee Corporation from San Ramon, California, did both the engineering and the construction management. Before engineering began the entire senior staff of the Plant Department was hired and assigned to the project. Senior staff included the Plant Superintendent, Plant General Foreman, Maintenance General Foreman and Chief Metallurgist. Gold Fields does not employ an internal central engineering staff to design their plants. We feel that the people who design the plant should be the ones who will be required to run it once it has been commissioned. This philosophy affords a continuous accountability from start of design through commissioning and operations. All four of the senior staff spent the most critical phase of the engineering stage at Davy McKee, so the plant is truly a reflection of all four disciplines. In bringing on the Maintenance General Foreman from the start, there was a focus placed on ease of maintaining the plant. Another philosophy that was adopted from the start was that the plant be easy to work in and maintain for both operators and maintenance personnel. Numerous design criteria were given to Davy McKee to ensure this. For example, we required that every piece of equipment could be reached easily with a crane or fork lift. All conveyors were required to have walkways on both sides for ease of maintenance and a minimum of 30 inches of clearance under them for ease of cleanup. Visibility for operators was considered very important and the control rooms and general plant layout were designed with this in mind. A list of about 100 general rules were given to Davy McKee during the early layout meetings and these were held as the general design criteria throughout engineering and construction. While engineering was progressing in San Ramon, California, dump leach test work was being done at the site. Three 6 foot diameter fiberglass columns were constructed and filled to a 20 foot height with low grade ore. Leaching characteristics were determined and the dump leach design was based on information collected from these columns. Construction The major contractors on the project were The Industrial Company for the bulk of the piping and structural, EMKO on the electrical/ instrumentation and Hunewill for most of the earth work and leach pad construction. All plant operating and maintenance personnel were employed eight weeks before startup for intensive training. Instructors were Gold Fields personnel, including foremen, and Davy McKee engineers. On occasion, selected suppliers representatives were brought in to discuss major pieces of equipment. Project completion was targeted for January, 1988 at a projected cost of 78.9 million dollars. Actual startup was about 1 1/2 months ahead of schedule and slightly under budget. Full design capacity was achieved the first full month of operation. Crushing Run of mine ore is delivered to the crusher and dumped into a 90 ton hopper which is topped with a 30" X 30" opening stationary grizzly. Ore is fed to a 50" X 60" Telsmith jaw crusher with a 5' wide apron feeder. The closed size setting of the
Citation
APA:
(1989) Gold Recovery At Gold Fields - Chimney CreekMLA: Gold Recovery At Gold Fields - Chimney Creek. Society for Mining, Metallurgy & Exploration, 1989.