Heat Generation and Climatic Control in the Operation of Tunnel Boring Machines

Society for Mining, Metallurgy & Exploration
S. J. Bluhm
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
6
File Size:
410 KB
Publication Date:
Jan 1, 1997

Abstract

INTRODUCTION Lesotho is a mountainous area of southern Africa from which water is to be exported in an extensive tunnel system, to industrial regions inland. The related tunnelling project has involved a num- ber of drives using tunnel boring machines [TBMs] to excavate about 100 km of 5 m diameter water tunnels [von Glehn and Bluhm, 1995). This paper describes the ventilation and cooling of some of the tunnel drives from both the operational and design points-of-view with a particular focus on heat generation. There were many common features in all of the drives but this paper is focused mainly on the Hlotse drive which was 18,4 km long. The drives were ventilated using forced ventilation systems to provide appropriate air flow throughout the tunnels and face zones. In addition, the Hlotse drive required refrigeration equip- ment which provided chilled water to the tunnel. While the sec- ondary ventilation systems play an important role in gas and dust handling, the paper concentrates on the primary ventilation and cooling issues. The ventilation of these tunnels was an exacting exercise be- cause: • Rock temperatures and geothermal heat flow were high. • TBMs with relatively high power ratings were used. • Diesel locomotives were used. • Drives were relatively long. • High altitude meant a low air density. An important feature was the simulation and monitoring of the ventilation and heat flow components and the project was characterised by analysis, monitoring and ongoing tactical decision-making throughout the progress. The thermodynamics of the systems were complex because there were many interactive effects and analyses were carried out using special computer pro- grams. The monitoring confirmed the accuracy of the models, and in this manner it was possible to confidently ensure healthy and safe working conditions and still minimise costs. Local ambient climate conditions range from temperatures higher than 35 "C in summer to below -10 OC in winter. Based on available statistical data and the thermal storage/damping effects in the system, design summer ambient conditions were taken as 15 OC/25 "C wet-bulb/dry-bulb. The barometric pressure was 80 kPa and due to the altitude, the ambient air density was only 0,9 kg/m3. The local Authority specified a maximum in-tunnel wet- bulb temperature [at any point] of 32,O OC and a mean wet-bulb temperature [from all locations] of 27,5 OC maximum. The maxi- mum height of ground cover above the tunnel was 1 200 m and the maximum virgin rock temperature was 41 OC; see Figure 1. Diesel dilution criteria specified by the local Authority was a minimum of 0.1 m3/s per rated kW of diesel engine. Other requirements related to gases such as CO, CO2, NOx and CH4 [and the need for intrinsically safe equipment] but these are not of direct relevance to this paper. The actual average face advance was about 30 m/d with good days achieving 60 m/d and good months achieving 1 000 m [23 working days]. The original design tunnelling rate was 50 m/d. DESCRIPTION OF HLOTSE DRIVE VENTILATION AND COOLING SYSTEM The ventilation requirements in the tunnels were dictated by heat and diesel dilution needs. The best ventilation and cooling policy is generally a balance between using increased quantities of fresh air or refrigeration [or both]. In this particular scenario it turned out that, since the diesel emission criteria required large quantities of air, the refrigeration needs were modest. The drive was ventilated using a ducted, forced ventilation system from fans located at the portal. The maximum ventilation requirement was 51 m3/s when the drive was at 18.4 km. From a heat flow point of view, the worst scenario was a heat load of 3.5 MW when the drive was at 7 km. This was cooled by the ventilation air and a supply of chilled water to the tunnel. Refrigeration and chilled water system In the design phase, a detailed comparison was carried out between two general alternatives for providing refrigeration. First, was a system in which refrigeration sets and air coolers are installed on the TBM train; the refrigeration sets are cooled by condenser water piped to and from cooling towers at the portal. Second, was a system in which refrigeration water chillers are in- stalled at the portal and chilled water is piped into the tunnel. The detailed comparison indicated that the capital and running costs of the second system were at least 60 % lower than the in-tunnel plant. There were also many obvious practical benefits for favouring the portal system. The refrigeration plant supplied 23 11s of cold water at a temperature of 10 OC. After providing the cooling effect in the drive, the water returned to the portal where it was initially cooled in open-circuit evaporative pre-cooling towers, chilled in the refrigeration plant and then returned to the tunnel. The cold water flowed into the tunnel in an insulated supply pipe and returned in an uninsulated pipe; the water was simply circulated to the end of the pipe and returned. The cooling effect in the tunnel was achieved entirely through heat transfer from the pipe [long linear heat exchanger] and no air coils or other heat exchangers were required. The cooling requirements were satisfied by the heat transfer to the returns chilled water steel pipe [200 mm]. The pipes were eventually installed to a maximum distance of 10,8 km in what was considered a very practical and cost effective solution.
Citation

APA: S. J. Bluhm  (1997)  Heat Generation and Climatic Control in the Operation of Tunnel Boring Machines

MLA: S. J. Bluhm Heat Generation and Climatic Control in the Operation of Tunnel Boring Machines. Society for Mining, Metallurgy & Exploration, 1997.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account