Hedges Gold Pty. Ltd. Tailings Disposal Dam Design, Performance, Operating Philosophy and Rehabilitation Plans

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 6
- File Size:
- 631 KB
- Publication Date:
- Jan 1, 1992
Abstract
Hedges Gold Pty. Ltd. mines and
processes a lateritic gold orebody approximately 120 km south east of Perth in the Darling plateau.
The operation is approximately 26 km from the town of Boddington and 31 km from the town of Dwellingup.
Hedges operates under The Western Australian Environmental Protection Act, Licence Number 3183.
Presently, nine Limitations and
Conditions are applicable to the
tailings dam. These conditions
apply to maximum discharge/disposal quantity permitted.
Hedges mine is located in state
Forest within the eastern, low
rainfall section of the Darling
Range and within the waler
catchment area of the Murray River.
Ore is carted by 120 tonne
haulpacks to the plant. The plant and tailings dam is on private farm land some six kms from the mine.
Citation
APA:
(1992) Hedges Gold Pty. Ltd. Tailings Disposal Dam Design, Performance, Operating Philosophy and Rehabilitation PlansMLA: Hedges Gold Pty. Ltd. Tailings Disposal Dam Design, Performance, Operating Philosophy and Rehabilitation Plans . Society for Mining, Metallurgy & Exploration, 1992.