High Risk Tunneling Adjacent To Large Water Tank On The UNWI Sections 3&4 Project

Society for Mining, Metallurgy & Exploration
Andrew Finney
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
9
File Size:
276 KB
Publication Date:

Abstract

INTRODUCTION The Sacramento Regional County Sanitation District (SRCSD) serves unincorporated areas of Sacramento County, parts of the cities of Sacramento and Folsom, and the cities of Citrus Heights, West Sacramento, Rancho Cordova, and Elk Grove. SRCSD maintains 145 kilometers (km) (90 miles) of interceptors that convey a combined total of 0.6 million meters3 per day (160 million gallons per day) or more of waste-water, with additional miles of sewer interceptors that are scheduled to be built by 2020. Wastewater is conveyed to the Sacramento Regional Wastewater Treatment Plant in the southwestern portion of the County, also managed and operated by SRCSD, in interceptors with diameters as large as 3.0 m (120 inches.) As part of its overall expansion program, SRCSD has constructed a number of major interceptors over the last few years with tunneling methods due to concerns associated with either the impacts of open cut construction in an urban environment (traffic, safety, noise, environmental concerns) or the need to achieve a crossing of a stream, river, or transportation corridor. This paper focuses on a specific issue that affected construction of the Upper Northwest Interceptor (UNWI) Sections 3&4 project, located at the northern limit of the SRCSD service boundary and within the limits of the City of Sacramento. This project involved the construction of 3.2 km (2 miles) of 2.1-meter (84-inch) and 2.4 km (1.5 miles) of 1.7-meter (66-inch) diameter reinforced concrete pipe (RCP) using MTBM, EPBM, and 3.3-meter (130-inch) two-pass TBM methods. The owner elected to install the RCP using tunneling for a number of reasons including a desire to avoid traffic impacts in a dense urban corridor, to minimize disturbance to the neighborhood, and to avoid potential dewatering-induced settlement issues along the western one-third of the project. For the western portion of the alignment the 2.1-meter (84-inch) reinforced concrete interceptor pipe was to be installed using a 2.7-meter (105-inch) earth pressure balance machine (EPBM). No external dewatering of shafts or tunnels was permitted for reasons of concern about settlement, discussed previously. At the intersection of Elkhorn Boulevard and Natomas Boulevard (at the extreme northwest corner of the project) the 2.7-meter (105-inch) EPBM tunneled past a recently constructed 11-million liter (3-million gallon) water storage reservoir, passing within 3 meters (10 feet) of the tank?s shallow foundation while tunneling through clean sands with a shallow groundwater table. The paper will discuss the implemented solution to mitigate additional settlement risk that was developed as a joint collaboration between the owner, CM, designer, and contractor.
Citation

APA: Andrew Finney  High Risk Tunneling Adjacent To Large Water Tank On The UNWI Sections 3&4 Project

MLA: Andrew Finney High Risk Tunneling Adjacent To Large Water Tank On The UNWI Sections 3&4 Project. Society for Mining, Metallurgy & Exploration,

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account