Abstract
With increased emphasis on controlled blasting, which is the first and least-costly stage of comminution, ore grindability and plant throughput can be increased by 5% to 10%, and energy savings of up to 10% appear possible. Crushing and grinding efficiencies are presented for ore blasted under regular and adjusted field conditions. An economic analysis of drilling and blasting through crushing and grinding is presented, suggesting that cost savings approaching 10% may be achieved
Citation
APA: