Innovative mining method, related blasting system and quality assurance for large underground crusher excavation Freeport DOZ Mine, West Papua Indonesia

- Organization:
- International Society of Explosives Engineers
- Pages:
- 10
- File Size:
- 979 KB
- Publication Date:
- Jan 1, 2007
Abstract
Several areas at the DOZ haulage were observed for the crusher’s location. Initially the new crusher designed position was west of the crusher 1, but due to concerns of the mine crack zone (deep MLZ) the crusher position moved to the south. The new crusher location is situated in a diorite rock massive between 3053 – 3079 levels, with the overall excavation of 2500 cum and dimension of 14m long, 14 m wide and 14 m high. Main Crusher chamber itself excavated by development jumbo in three lifts. Development of access to the bottom crusher was developing the same time as chambering the top crusher. The pocket of the crusher mined with vertical crater retreat system which is initiated in one time after middle slot raise. Collaboration between production and perimeter blast holes to be obtaining in control the actual cuts as per the design shape.
Citation
APA:
(2007) Innovative mining method, related blasting system and quality assurance for large underground crusher excavation Freeport DOZ Mine, West Papua IndonesiaMLA: Innovative mining method, related blasting system and quality assurance for large underground crusher excavation Freeport DOZ Mine, West Papua Indonesia. International Society of Explosives Engineers, 2007.