Innovative Rehabilitation of Existing Tunnels under Minimum Impact on Operation

Society for Mining, Metallurgy & Exploration
A. G. Nitschke J. Dase I. Ossenbühl W. Dolsak
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
7
File Size:
1382 KB
Publication Date:
Jan 1, 2015

Abstract

"The authors have successfully developed an innovative rehabilitation concept, which meets actual technical standards and minimizes the impact on the operation of a key conveyor tunnel. A flexible and stepwise ground support rehabilitation program utilized a combination of yielding steel arch sections with grout filled fabric hoses, which represents a fast and safe backfilling support system. The system was developed and successfully installed at Bingham Canyon Mine, the world’s largest open pit copper mine, which also includes numerous underground structures. The mine is owned and operated by Kennecott Utah Copper (RTKC) a fully owned subsidiary of Rio Tinto. The system was implemented at a conveyance tunnel, which was originally designed as a railroad tunnel, but was re-commissioned and is currently used as a conveyor belt tunnel to transport ore from the open pit to processing facilities outside the mine. The existing structure showed signs of overstressing due to movements in the surrounding rock mass, which had to be addressed with a yielding support system in order to provide safe access into the tunnel. However, the impact on the conveyor belt operation due to support installation was to be limited to the bare minimum. Keywords: rehabilitation, yielding support, mining, stabilization, and grout filled fabric hose.PROJECT DESCRIPTION The C6 Tunnel is considered a critical asset for the operation of the Bingham Canyon mine as it comprises the standard route for transporting crushed ore from the open pit to the processing facility on a continuous conveyor belt system. The C6 tunnel was originally built as a railroad tunnel. Construction was completed in 1959. The original horse-shoe shaped cross section of the tunnel was 18 feet wide and 24-1/2 feet high [8]. The tunnel length was approximately 18,000 feet. During its service life, the railroad tunnel has undergone several transformations. The length of the tunnel towards the Bingham Canyon pit was shortened over the course of mining operations and the railroad tracks in the tunnel were removed. The invert was partially backfilled (3 feet typical) and a 72 inches belt conveyor was installed. Currently, the C6 Tunnel is nominally only approximately 21 feet high and 15,000 feet long. Ground Support and Rehabilitation Measures prior to 2014 The C6 tunnel was mined mainly with conventional mining methods, using drill & blast as the typical one. However, the weak geological sections, such as those encountered in the Fortuna fault, were excavated by shaping and chipping with machine-held moils [8]."
Citation

APA: A. G. Nitschke J. Dase I. Ossenbühl W. Dolsak  (2015)  Innovative Rehabilitation of Existing Tunnels under Minimum Impact on Operation

MLA: A. G. Nitschke J. Dase I. Ossenbühl W. Dolsak Innovative Rehabilitation of Existing Tunnels under Minimum Impact on Operation. Society for Mining, Metallurgy & Exploration, 2015.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account