Integrated Process Control System at Gold Fields Operating Co. - Chimney Creek Mine

Society for Mining, Metallurgy & Exploration
John O. Marsden Michael F. Gleason Cindy S. Jones James R. Arnold John G. Mansanti
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
14
File Size:
621 KB
Publication Date:
Jan 1, 1990

Abstract

INTRODUCTION The Chimney Creek Gold Mine (Gold Fields Operating Co. - Chimney Creek) is located 47 miles northeast of Winnemucca, Nevada, at the northern end of the Osgood Mountains. The operation is a wholly owned subsidiary of Gold Fields Mining Corporation, the North American branch of Consolidated Gold Fields PLC, London, England. The plant started up in November, 1987, less than three years after discovery of the orebody and three months ahead of schedule. Ore is mined in an open pit and is processed by combined dump leaching and milling techniques for gold and silver recovery. The mine is set to produce approximately 150.000 ounces of gold and 50,000 ounces of silver per year over a 12 year life at current reserve estimations. The mine was designed and constructed at a cost of $79.3 million with engineering and construction services provided by Davy McKee Corporation, San Ramon, California. Key Gold Fields operating staff were involved in the design of the facility from the start of the project: The Mine Manager, Plant Superintendent, Plant General Foreman, Maintenance General Foreman and Chief Metallurgist were all involved full time on the project within 5 months of the first ore discovery. Emphasis was directed at optimizing operating efficiency and in particular minimizing labor costs in the plant. It was recognized that a high level of instrumentation and control would be required to achieve this. The risk associated with the instrumentation and control systems implemented was to be minimized by using equipment and systems that had been proven in industry while utilizing the most cost effective, state-of-the-art technology available. The reliability of the overall control system was considered to be critical in view of the cost of downtime associated with the gold extraction plant. BRIEF PROCESS DESCRIPTION The dump leaching process treats approximately 1.2 million tons per year of low grade ore at an average grade of 0.035 oz/ton. Run of mine material is dumped on a lined leach pad and weak cyanide solution is applied by drip irrigation. Pregnant solution run off is pumped to carbon columns in the milling plant for gold recovery and the barren solution returned to the dump leach circuit. Average gold recovery is 60%. This process has little instrumentation and control associated with it. The milling operation treats 700,000 tons annually of higher grade ore (0.200 oz/ton initially, dropping to an average of 0.135 oz/ton after first two years). Recovery is directly related to head grade (fixed tail assay effect) and currently averages 96%. A single pass through a jaw crusher reduces run of mine ore to minus 12 inches. The ore is stockpiled and reclaimed by loader for grinding in a two-stage milling circuit consisting of a SAG mill and ball mill, the latter in closed circuit with hydrocyclones. Cyanide and lime are added into the SAG mill to start dissolution of gold as early as possible in the circuit. The ground product leaves the milling circuit at approximately 78% minus 200 mesh and is fed to an unique "double thickener" leaching-recovery circuit. This circuit has been discussed in detail in a paper by J. G. Mansanti et a1 (1). Two thickeners are arranged in counter- current configuration with three leach tanks. Overflow solution from the first thickener is treated by carbon-in-columns (CIC) for gold recovery with 85% of the soluble gold recovered onto this carbon. Underflow slurry from this thickener is pumped to the leach tanks, with a total retention time of 12 hours, and then gravitates to the No. 2 thickener. Overflow solution from the second thickener is used as a wash in the first thickener. Underflow slurry from the second thickener is treated in a carbon-in- pulp (CIP) scavenging circuit to recover the remaining 15% dissolved gold. Gold-loaded carbon from both the dump leach and milling circuits is stripped in batches using the Zadra hot caustic- cyanide elution process. Gold (and silver) is recovered from the hot strip solution by precipitation with zinc dust and the product recovered on Funda pressure filters. The precipitate is retorted to remove any mercury and then smelted into buttons. The buttons (approximately 80% gold, 15% silver) are shipped to an independent refiner in Salt Lake City, Utah, for further treatment.
Citation

APA: John O. Marsden Michael F. Gleason Cindy S. Jones James R. Arnold John G. Mansanti  (1990)  Integrated Process Control System at Gold Fields Operating Co. - Chimney Creek Mine

MLA: John O. Marsden Michael F. Gleason Cindy S. Jones James R. Arnold John G. Mansanti Integrated Process Control System at Gold Fields Operating Co. - Chimney Creek Mine. Society for Mining, Metallurgy & Exploration, 1990.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account