Lake Mead intake No. 3: TBM tunneling at high pressure (ed38a026-61b2-4fb1-96a2-f8a5edcaaf6a)

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 8
- File Size:
- 7007 KB
- Publication Date:
- Jan 1, 2015
Abstract
"In response to the severe drought on the Colorado River basin and in order to preserve existing water capacity to the Las Vegas Valley, the Southern Nevada Water Authority contracted a new deep-water intake (Intake No. 3) located in Lake Mead. The current project (Contract No. 070F-01-C1) includes 5 km (3 miles) of tunnel with very difficult geological conditions and a 200- m (650-ft) deep shaft and marine works. This paper will present the current status of the design-build contract being constructed by Vegas Tunnel Constructors and the challenges and problems faced and the innovative solutions developed to handle the difficult conditions encountered during tunneling with up to 15 bars of pressure.ProjectbackgroundThe Las Vegas Valley receives the majority of its water from Lake Mead, which is located approximately 30 km (20 miles) east of the Las Vegas, NV metropolitan area. Due to the severe drought that has hit the southwest region of the United States, the water level in Lake Mead has receded from its high water level of 372 m (1,221 ft) above mean sea level (amsl) to a low of 330 m (1,076 ft) amsl in June 2015. Should the lake level continue to fall, at elevation 320 m (1,050 ft) amsl, the current water intakes will not be able to draw enough water to meet the needs of the local area. The risk of losing water capacity has prompted the construction of a new deeper intake. Not only is the new Intake No. 3 situated at a lower elevation in the lake at 262 m (860 ft) amsl, the new Intake No. 3 is also located to draw better quality (Fig. 1).Project challengesThe project has had several difficult challenges to overcome:• The work consisted of a 1.2 kt (1,300 st) structure constructed on a barge and lowered 100 m (330 ft) into Lake Mead anchored with 9,200 m3 (12,200 cu yd) of tremie concrete.• The drill-and-blast starter tunnel was impacted by three inflow events, resulting in a one-year project delay.• One of the main challenges was selecting the tunnel boring machine (TBM) and excavating the tunnel with expected hydraulic head pressure of as much as 17 bar (16 bar was the highest pressure recorded during the drive), crossing faulted areas, low rock cover and the risk of tunnel instability due to direct connection with the lake.• Extensive pre-excavation grouting with a constant head pressure ranging from 12 bar to 15 bar.• Structural repair of the cutterhead in difficult hydrogeological conditions [water inflow of approx. 800 m3/hr (4,000 gpm)].• Complete repair of the cascade sealing system for the main bearing and two replacements of the pinion bearings.• The TBM approach to the intake structure."
Citation
APA:
(2015) Lake Mead intake No. 3: TBM tunneling at high pressure (ed38a026-61b2-4fb1-96a2-f8a5edcaaf6a)MLA: Lake Mead intake No. 3: TBM tunneling at high pressure (ed38a026-61b2-4fb1-96a2-f8a5edcaaf6a). Society for Mining, Metallurgy & Exploration, 2015.