Macassa No. 3 Shaft - Deep Shaft Sinking By Conventional Methods ? Introduction

Society for Mining, Metallurgy & Exploration
F. A. Edwards
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
9
File Size:
1248 KB
Publication Date:
Jan 1, 1985

Abstract

The Macassa Division of Lac Minerals Ltd. is a high grade gold mine that has been operating in Kirkland Lake, Ontario for the past 51 years. It produces approximately 120,000 tonnes of ore per year, averaging approximately 18.7 grams per tonne (0.45 ounces per ton) of gold. Over the years, the ore body has been developed to a point where mining takes place below the 1,220 m (4,000 feet) elevation and 1,830 m elevation (6,000 feet) west of the original shaft. The mine is currently serviced by two surface and two winze shafts. (Figure 1). The ore body extends below the 1,930 m (6,400 feet) Level which is the bottom of the existing mining operation. An ambitious underground exploration program has substantially increased these reserves. Concurrent with the discovery of greater reserves, has been rapidly escalating mining costs, particularly labour which constituted 66% of the total cost in 1981. These costs continued to escalate as the major proportion of mining was carried out to the west, far away from the existing hoisting systems. This required a three lift hoisting system for men, materials and ore. In addition to the increased travel time and ore handling expense, increased humidity, temperature, ventilation and compressed air losses have added to the inefficiency of the operation. As a result, studies were initiated in 1980 to assess the future of the Macassa operation. The results of the studies indicated that a new deep shaft with a potential to hoist from 2,135 m (7,000 feet) or below was the most attractive option. Detailed design of the shaft and associated surface plant commenced in January, 1982 and the following milestone dates were achieved: 1980 - initial study of hoisting and haulage facilities; January, 1981 - ore reserves in excess of 1 million tonnes of ore at 18.7 g/tonne (0.45 oz/ton) confirmed; March, 1982 - preliminary study of Macassa No. 3 Shaft completed; April, 1982 - permanent hoisting plant purchased; June, 1982 - site clearing commenced; September, 1982 - shaft collared; May 1, 1983 - shaft sinking commenced; February 11, 1985 - shaft reached 1,600 m (1mile); December 1, 1985 - shaft scheduled for completion.
Citation

APA: F. A. Edwards  (1985)  Macassa No. 3 Shaft - Deep Shaft Sinking By Conventional Methods ? Introduction

MLA: F. A. Edwards Macassa No. 3 Shaft - Deep Shaft Sinking By Conventional Methods ? Introduction. Society for Mining, Metallurgy & Exploration, 1985.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account