Manila Aqueduct (Philippines) — The Construction of the Umiray-Angat Tunnel Project — A Success of Organisation and Technology Against a Unique Combination of the Most Adverse Conditions Ever Encountered in Tunneling

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 14
- File Size:
- 4060 KB
- Publication Date:
- Jan 1, 2001
Abstract
The Umiray Angat 13,2 km long tunnel in Philippines have been bored through extremely variable and difficult ground conditions including a number of special events. In particular the following adverse conditions were found: faults in decomposed ground, high temperature rocks, extremely rapid and important convergence phenomena, water inflows up to 800 litres per second. The special El Nino climatic conditions caused a long dry season and lower the level of the lake that was granting the access by barge to the site under the minimum navigable level. Many equipment have had therefore to be transported to site by a 10 ton capacity helicopter, after having been partially dismounted. For the same reason most of the tunnel drive have been bored servicing the site by 1 ton capacity helicopters to transport materials, spares and personnel. In order to overcome the above geological and logistic problems several innovation were introduced and tested in this project. Despite all that difficulties the 13,2 km of tunnel were bored in about 24 months, with a global average of 500 m/month.
Citation
APA:
(2001) Manila Aqueduct (Philippines) — The Construction of the Umiray-Angat Tunnel Project — A Success of Organisation and Technology Against a Unique Combination of the Most Adverse Conditions Ever Encountered in TunnelingMLA: Manila Aqueduct (Philippines) — The Construction of the Umiray-Angat Tunnel Project — A Success of Organisation and Technology Against a Unique Combination of the Most Adverse Conditions Ever Encountered in Tunneling. Society for Mining, Metallurgy & Exploration, 2001.