Maximising the Capacity of the Ore Handling Systems at Xstrata CopperÆs Mount Isa Copper Operations

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 8
- File Size:
- 1068 KB
- Publication Date:
- Jan 1, 2005
Abstract
The current copper ore handling systems in use at Xstrata CopperÆs Mount Isa Copper Operations are up to 33 years old and have hoisted over 160 Mt at a rate of around 6 Mtpa. The mineÆs production profile is increasing in line with the optimum life of mine plan to over 6.6 Mtpa, which requires a system utilisation and reliability above that previously achieved. Copper ore is hoisted up the U62 shaft, which forms the central part of the U62 ore handling system. In theory this system can cope with the duty planned if the bottleneck is only the U62 winder. To achieve the planned production rate will require increased focus on reliability of each component in the ore handling system so that ore is available at the shaft for hoisting whenever the shaft is available, and the shaft is available for the maximum practical time. Increased availability will be achieved through the outcomes of the study of each component in the U62 system, and the internal ore handling systems that deliver ore from as far as 2 km laterally and 700 m vertically from the U62 shaft. The true capacity of each component is being determined and current performance is being measured with the aim of improving performance through root cause analysis and engineering out the causes of delays. The program began in March 2004 and this paper describes the progress achieved as of April 2005.
Citation
APA:
(2005) Maximising the Capacity of the Ore Handling Systems at Xstrata CopperÆs Mount Isa Copper OperationsMLA: Maximising the Capacity of the Ore Handling Systems at Xstrata CopperÆs Mount Isa Copper Operations. The Australasian Institute of Mining and Metallurgy, 2005.