Metal Mining - Mine Drainage at Eureka Corp., Ltd., Eureka, Nev.

The American Institute of Mining, Metallurgical, and Petroleum Engineers
George W. Mitchell
Organization:
The American Institute of Mining, Metallurgical, and Petroleum Engineers
Pages:
6
File Size:
533 KB
Publication Date:
Jan 1, 1954

Abstract

THE property of Eureka Corp. Ltd. is located in the approximate geographic center of Nevada, 2 miles from Eureka, the county seat. The great sources of power, the Colorado, Snake, and Salmon Rivers and the rivers of northern California, are 300 to 500 miles distant, and no lines serve areas closer than 150 miles. Fuel for diesel and steam generation is available in Utah, 300 to 400 miles to the east. Eureka's railhead is 80 miles north where two trunk lines cross the county. A spur line serves Ely, 77 miles east. Good highways connect Eureka to the railheads. Activity in the Eureka mining district began in the early 1870's. The oxidized high grade lead-sil-ver-gold ore terminated against the footwall of the Ruby Hill fault, and in 1890 the main operations ceased. In 1938 Eureka Corp. Ltd. discovered ore in the hanging wall of the fault by diamond drilling. The history of Eureka in the late 1800's indicates that there was some water at 600 to 800 ft in the old workings, probably accumulations above the water table which did not seriously interfere with mining operations. Both the Locan and Richmond shafts were sunk to a level below the table, but apparently the only serious difficulty with water occurred in the Locan. The steam pump used when the last work was done on the 1200 level in 1923, many years after exhaustion of the main orebodies, is still installed on the Locan 900 level. The capacity was about 500 gpm, lifting 750 ft to the 100 level, which connected with the surface. In addition to this. bailers were used to keep the 1200 level free of water. It is said that pumping in 1923 lowered the water in the Holly shaft, about a mile and a half away, but this seems doubtful. The pumping was of short duration because no ore was found. When work at the new Fad shaft was started in 1941 Eureka Corp. Ltd. engineers were fully aware of the probability of encountering water in large volume. Their primary exploration and development had to be carried on at the 2250 level. The first water was encountered at 300 ft. This was undoubtedly surface drainage in the bedding of the Pogonip limestone and was less than 100 gpm. The fractured, loose Hamburg dolomite at the water table was not well cemented, and relatively little water, 300 gpm, percolated through it with difficulty. At 1350 ft well-cemented dolomite containing some open fractures was encountered. These fractures produced the first water of consequence, 750 gpm. At 1700 ft the volume was 1000 gpm increasing to the maximum during shaft sinking, 1600 gpm, at the 2000 level. Secret Canyon shale, a dry formation, was entered at 2100 ft, where a concrete water ring was placed to catch all of the water. The volume decreased rapidly to a constant flow of 1200 gpm. Below 2100 ft the shaft and stations remained in the shale and water was not a problem. Several faults of moderate displacement, including the reverse Martin fault, had been intersected during the traversing of 1000 ft of wet Hamburg, but no undue quantities of water were encountered. Observations in the diamond drill holes in the ore zone area showed a rapid lowering of the water table. The shaft was flooded when it left the dry shale and entered the water-bearing Eldorado dolomite on the 2250 level, crossing a fissure which paralleled the Martin fault. High pressure water doubled the volume then being pumped. Pipe failure through a water door bulkhead was a contributing factor. Immediately following this flooding in March 1948 preparations were made to recover the shaft as rapidly as possible by increasing power and pump capacities as needed. Measurements before flooding indicated the water could be lowered at a fast rate. However, the water table did not recede as rapidly as expected and volumes required to lower the water in the shaft were higher. Obviously the size of the main water channel on the 2250 level was increasing because of erosion, allowing greater volumes to enter the workings and draining beyond the cone originally being drained during shaft sinking. Eroded material was being deposited in the shaft below the 2250 level in serious proportions. In December 1948 a second flooding of the Fad shaft was allowed for the purpose of reassessing existing conditions and studying alternate methods of attack. The detailed geology of the Eureka mining district, see Fig. 1, has been described during the past 75 years by many geologists.' Only the general features and those which seem to affect the drainage problem will be discussed. The old ore zone, mined between 1870 and 1890, is located in a wedge-shaped block of Eldorado dolomite between the footwall of the Ruby Hill fault and the underlying Prospect Mountain quartzite, see Fig. 2. Production of high grade oxidized lead ore containing high values in gold and silver has been variously estimated at $50 to $90 million. The tonnage mined was probably close to 1,500,000, nearly all of which was found above the water table. The new ore, discovered by diamond drilling in the hanging wall of the Ruby Hill fault, is a flat-
Citation

APA: George W. Mitchell  (1954)  Metal Mining - Mine Drainage at Eureka Corp., Ltd., Eureka, Nev.

MLA: George W. Mitchell Metal Mining - Mine Drainage at Eureka Corp., Ltd., Eureka, Nev.. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1954.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account