Mission Mine Goes To Work

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 2
- File Size:
- 358 KB
- Publication Date:
- Jan 9, 1961
Abstract
On July 25, the first copper ore From American Smelting & Refining Co.'s Mission open pit nine was sent into the new 15,000-tpd concentrator : three clays later, the first rail cars containing the Mission concentrate were sent north to the smelter at Hayden, Ariz. Thus two y,ears after stripping was started, Asarco's new mine, located south of Tucson. went on stream several months ahead of schedule. The plant, designed and constructed by Western Knapp Engineering Co., is expected to be operating at full capacity about September 1. with present plans calling for the copper concentrate from Mission to be shipped to Asarco's smelters at Hayden and El Paso.