NATM Through Clean Sands—The Michigan Street Experience

Society for Mining, Metallurgy & Exploration
Paul H. Madsen Mohamed A. Younis Vojtech Gall Paul J. Headland
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
10
File Size:
234 KB
Publication Date:
Jan 1, 2007

Abstract

INTRODUCTION A 100 ft long, 20 ft high and 18 ft wide NATM tunnel was excavated through grouted clean sands beneath a busy city street, including a variety of existing utility lines. The new tunnel associated with a hospital expansion will serve as a pedestrian tunnel connecting a parking structure with a new hospital facility. Tunnel construction started on December 15, 2005 when drilling for the grouting program started and was completed on May 26, 2006 when the tunnel final lining was completed. The tunnel was constructed by Kiewit Construction Company as a tunnel subcontractor to The Christman Company who is constructing the hospital facility for Spectrum Health in Grand Rapids, Michigan. URS was the project designer. GallZeidler Consultants, LLC were the contractor’s NATM consultant. PROJECT DESCRIPTION The Michigan Street Pedestrian Tunnel is a component of the Michigan Street Development located along the north side of Michigan Street NE between Coit Avenue NE and North Division Avenue in the downtown area of the Grand Rapids, Michigan. The Michigan Street Development includes a parking deck and four new towers to be constructed over the proposed parking deck. The tower planned furthest east is being developed by Spectrum Health as the Lemmen-Holton Cancer Pavillion. The purpose of the pedestrian tunnel is to connect the proposed Lemmen-Holton Cancer Pavillion with the future Spectrum building to be located on the south side of Michigan Street NE. The southern end of the tunnel was constructed with a bulkhead until the future Spectrum building is constructed at which time interconnection will be required. The tunnel site plan and profile are shown in Figure 1, Site Plan, and Figure 2, Tunnel Profile. Several challenges were faced during the design and construction of the Michigan Street Pedestrian Tunnel. These challenges included compressed design and construction schedule, maintenance of traffic and protection of old underground utilities. The tunnel was being constructed as part of the Michigan Street Development and coordination with other concurrent construction activities was required. The tunnel was constructed within a specified window of time to allow other associated construction activities to take place without compromising the overall project schedule. The design started in June 2005 and construction was completed by June 2006.
Citation

APA: Paul H. Madsen Mohamed A. Younis Vojtech Gall Paul J. Headland  (2007)  NATM Through Clean Sands—The Michigan Street Experience

MLA: Paul H. Madsen Mohamed A. Younis Vojtech Gall Paul J. Headland NATM Through Clean Sands—The Michigan Street Experience. Society for Mining, Metallurgy & Exploration, 2007.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account