Need For Improvements Sparks Continued Tests At Berkeley Pit

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 4
- File Size:
- 409 KB
- Publication Date:
- Jan 7, 1961
Abstract
Anaconda's Berkeley pit at Butte produces 34,000 tpd of ore averaging 0.8 pct copper. Two-and-one-half tons of waste is stripped per ton of ore, approximately 40,000 tpd by the company and an added 45,000 tons by the F&S Contracting Co. The company truck fleet consists of 24 Euclid and 18 Mack 34-ton, rear-dump diesel trucks.