No. 1 Queens Road - Melbourne, Australia

- Organization:
- Deep Foundations Institute
- Pages:
- 4
- File Size:
- 549 KB
- Publication Date:
- Jan 1, 2005
Abstract
"INTRODUCTIONNo. 1 Queens Rd was an existing 10-storey office building founded on large pad footings. This project involved the construction of a 6-level, 15m (50-ft.) deep basement excavated immediately adjacent to the existing building and also beneath the existing footprint of the Southern end of the building. The total perimeter of the new basement was to be approximately 200m (656 ft.) all with a retained height of 15m (50 ft.). It was also proposed to add a further 5 storeys to the building. Approximately 18 of the existing columns supporting the 10-storey building were to have the applied column load diverted from the existing foundations at ground level onto the new piles or basement raft 15m (50 ft.) below.The geotechnical profile consisted of fill for the top 1.5m predominately comprising of clayey sand with a high gravel content from 1.5m to 9m (5 to 30 ft.), a medium dense to dense clayey sand and then below was a sandy clay extending to 15m (50 ft.) ranging from stiff to very stiff. From 15m on completely to extremely weathered siltstone was encountered. The groundwater was measured at 9.5m (31 ft.) below the natural ground surface.DESIGN BRIEFThe existing building columns were founded on large pad foundations up to 4.4m (14.5 ft.) square, founded on the dense clayey sand. These pads would require temporary support to enable the excavation to proceed beneath them. Upon completion of the excavation under the pads new columns were to be constructed joining into the existing columns to transfer the load onto the new raft slab, 15m (50 ft.) below. The existing 10 floors were to be refurbished. It was planned to undertake all the temporary support and transferring of loads while the structure above was only able to provide a dead load. It was decided that any movement of the building would have minimum impact on a skeleton structure. During the temporary support of the columns, movements due to construction activities had to be monitored to understand any potential stresses in the structure above.The original design required beams to be installed under the pads and supported at either end by temporary piles that were to be founded below the level of the proposed excavation. (Refer to sketch 1). Wagstaff Piling considered that this methodology had difficulties in construction at all stages and did not provide facility for transfer of the load without significant movement of the structure above. Wagstaff Piling revised the design to attach beams to the columns above the pads using shear collars. (Refer to sketch 2). These beams supported on the temporary piles could then be jacked upwards to remove loads off the pads. This would enable removal of the pads with minimal movement of the 10-storey building above. (Refer to photo 1 and back cover photo)."
Citation
APA:
(2005) No. 1 Queens Road - Melbourne, AustraliaMLA: No. 1 Queens Road - Melbourne, Australia. Deep Foundations Institute, 2005.