Noranda's Bell Allard pastefill plant: commissioning and beyond

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 20
- File Size:
- 2028 KB
- Publication Date:
- Jan 1, 2002
Abstract
"The pastefill circuit at the Bell Allard Mine in Matagami, Quebec started up in August 1999. The surface pastefill plant produces a cemented paste which is sent underground by gravity through a vertical pipeline in the mine ventilation shaft. Difficulties with paste flow during the start-up highlighted the importance of understanding paste rheology and the effect of operating procedures on line wear. By June 2000, the original circuit had been modified to include a paste pump to transport the paste to the shaft.The steps taken during the paste plant commissioning are discussed. The final flow sheet is presented, focussing on the use of instrumentation to ensure full column flow and proper distribution underground. Resistance modelling and accelerated curing of samples are examined as possible ways of predicting paste resistance to ensure compliance with the mine’s paste specifications.INTRODUCTIONCommissioning a new plant can be difficult and time consuming. The start-up of Noranda’s Bell Allard paste backfill plant was no exception. Since the first day it went into operation, the paste circuit could not meet the tonnage and paste quality requirements of the mine because the paste would not flow by gravity into the vertical pipeline in the mine’s ventilation shaft.Diagnosis of the pastefill problems proved difficult. It was only when the rheology of the Bell Allard paste was understood that the flow problems were solved. To ensure that the paste placed in the stopes meets mine requirements, two methods of paste resistance prediction are being developed."
Citation
APA:
(2002) Noranda's Bell Allard pastefill plant: commissioning and beyondMLA: Noranda's Bell Allard pastefill plant: commissioning and beyond. Canadian Institute of Mining, Metallurgy and Petroleum, 2002.