OFR-122(2)-80 Alumina Process Feasibility Study And Preliminary Pilot Plant Design - Task 3 Report: Preliminary Design Of 25 Ton Per Day Pilot Plant - Volume II - Appendix A - Equipment List, Specifications - And Quotations - Areas 1 - 7 ? Intro

- Organization:
- The National Institute for Occupational Safety and Health (NIOSH)
- Pages:
- 284
- File Size:
- 60578 KB
- Publication Date:
- Jan 1, 1979
Abstract
This appendix contains the list of equipment selected for the capitol cost estimate, with the respective quotations from their vendors/manufacturers. A vendor response report along with a separate equipment and motor list has been included in the first part of this appendix.
Citation
APA: (1979) OFR-122(2)-80 Alumina Process Feasibility Study And Preliminary Pilot Plant Design - Task 3 Report: Preliminary Design Of 25 Ton Per Day Pilot Plant - Volume II - Appendix A - Equipment List, Specifications - And Quotations - Areas 1 - 7 ? Intro
MLA: OFR-122(2)-80 Alumina Process Feasibility Study And Preliminary Pilot Plant Design - Task 3 Report: Preliminary Design Of 25 Ton Per Day Pilot Plant - Volume II - Appendix A - Equipment List, Specifications - And Quotations - Areas 1 - 7 ? Intro. The National Institute for Occupational Safety and Health (NIOSH), 1979.