Abstract
The logic and capabilities of a long-term production planning method for open pit mining are presented. This is a new method that can be used to obtain simultaneous solutions to the four interrelated parameters of open pit mining: mine life, specific blocks to be mined each year, the amount of ore and waste to be mined each year, and the ultimate pit limits. An efficient milling cutoff grade can also be obtained through a systematic analysis. A production plan for a real-life gold deposit is given to illustrate the logic and the capabilities of the method.
Citation
APA: