Optimization In Large Tunnels

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 7
- File Size:
- 401 KB
- Publication Date:
- Jan 1, 2005
Abstract
NTPC (National Thermal Power Corporation), a multi-unit organization, is generating 26% of India’s total power. This power is produced from its 14 coal based stations and 7 gas based stations. NTPC is entering into the business of power-distribution, power-trading, setting up of coal mines and diversification in non-conventional energy sector as well. For achieving the goal of the country “Power for All” NTPC has taken a giant stride by entering into Hydro Power generation which is also the cheapest and the cleanest renewable source of energy. In its pursuit for excellence, 800 MW Koldam Hydro Power Project is NTPC’s first venture in hydro sector. In Koldam, hydropower potential will be harnessed by constructing a 163m high earth and rock fill dam in a narrow gorge at upstream end of Bhakra reservoir. The river diversion is envisaged through two parallel, 14m finished diameter ‘horseshoe’ tunnels of length 901m and 934m at village Kian on the right bank, where the river forms a 180° loop. The diversion tunnels are designed to accommodate a flood of 6500m3/sec, taking into account the maximum probable discharge of 200 years return period. The tunnels pass through dolomite and limestone rock formations. The excavation of tunnels was done with drill and blast method. The excavation was attempted from both inlet and outlet faces. During geological investigation a rock fault was located at the outlet area. The location of the fault was such that it was passing through the edge of the Tunnel-1portal and around 30m away from the face of the Tunnel-2 portal. The quality of the rock at Inlet was also poor. To save the portals from slips, excavation of the tunnels was planned to start after the completion of the open excavation and its support system both at inlet and outlet. The tunnel excavation at inlet was envisaged by approaching the tunnels’ portal by constructing a road through 540EL bench and meeting the inlet portals on the upstream end, which would have been ready by mid2003, only after completion of the open excavation and its support system. To save time and cost, it was felt necessary to modify the planning by starting the tunnel excavation simultaneously along with open works both at inlet and outlet. The excavation at the inlet face of the tunnels started in December 2002 after rerouting the approach road to inlet portals through haulage road on the downstream and similarly Tunnel-1 at the outlet was started in the low cover area before completion of open area works. Thus the tunnel—heading excavation was started nearly 06 months early with the change of methodology.
Citation
APA:
(2005) Optimization In Large TunnelsMLA: Optimization In Large Tunnels. Society for Mining, Metallurgy & Exploration, 2005.