Our Efforts to Modernize an Archaic Mine Project Cost Estimating Software System

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 3
- File Size:
- 148 KB
- Publication Date:
- Jan 1, 2019
Abstract
In 1994 Western Mine Engineering, Inc., (WME), which is now InfoMine USA, Inc., set out to build a suite of stand-alone software programs that would provide their clients the means to estimate the costs of developing and operating mineral exploitation projects. After the first program (Sherpa for Surface Mines) was completed and launched, the developer (me) left WME to form Aventurine Engineering, Inc., in order to complete the series of applications. In the years since, four programs have either been developed or upgraded and enhanced. Applications were produced that estimate the costs of underground mining, placer mining, and project site reclamation. In addition, an application specifically designed to evaluate the economics of these projects, which was based upon a program previously developed for WME by Bill Willoughby of Willoughby & Associates, was redesigned and the code updated to a MicroSoft compatible platform.
All these programs follow an engineering-based approach to cost estimating. Instead of relying on rules-of-thumb and statistical averages, they calculate all of the engineering and operational parameters needed to estimate costs. The premise is that the uncertainty associated with cost estimates should lie with the data available for the resource, not the approaches used to design and estimate the associated design parameters. In other words, it is acceptable that items such as the resource grades, deposit dimensions, ore and wall rock characteristics, and mill recovery rates carry with them some uncertainty, but parameters such as loader bucket capacities, truck speeds, pump horsepowers, hoist velocities, and grinding mill diameters can be calculated (although uncertain data might be used in those calculations). No additional uncertainties should be introduced because the cost-estimating procedure relied upon statistical manipulation or anecdotal inaccuracies.
To that end, the programs rely upon calculation-based approaches to selecting and sizing machinery, assigning the required workforce, and determining the extent of the consumables needed to recover mineralized material at a rate defined by the client. And while calculation-based software is not unusual, more modern approaches work toward the development, accumulation, and manipulation of data.
INITIAL CONDITIONS AND PROJECT GOALS
In 2016 we had five separate programs completely disconnected from one another. Each was written in VisualBasic, a language that was falling from favor. In essence, the status in 2016 was a series of stand-alone programs (Figure 1) in which results from one needed to be manually entered as input into another.
Citation
APA:
(2019) Our Efforts to Modernize an Archaic Mine Project Cost Estimating Software SystemMLA: Our Efforts to Modernize an Archaic Mine Project Cost Estimating Software System. Society for Mining, Metallurgy & Exploration, 2019.