Permitting and compliance procedures outlined for Consol’s Bailey coal mine

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 3
- File Size:
- 563 KB
- Publication Date:
- Jan 9, 1985
Abstract
Introduction The Bailey mining complex is located in Greene County, PA, in the Talley Run valley. It includes two Pittsburgh No. 8 seam deep mines (Bailey and Bailey No. 2), a coal preparation plant, and two refuse areas. Clean coal is shipped from the complex by way of a 24-km (15-mile) rail spur. It con¬nects to the Monongahela Railroad in Waynesburg, PA. In early 1981, Consolidation Coal Co. (Consol) began a permitting effort aimed at building the mine. Construction began in Dec. 1981, less than six months after the first application submittal. Clean coal was produced by the Bailey preparation plant in Sept. 1984. Several factors allowed quick permitting at Bailey. Effective project planning, including early formulation of a project planning team, and identification of red flag issues helped. So did innovative responses to environmental questions, and development of environmentally sound project designs. Forming a project planning team Consol management decided that Bailey mine construction had to begin in late 1981. A project permitting team was immediately formed to see that this goal was achieved. Team members included a project manager and personnel from Consol's engineering, environmental, and operating departments. Communications among all team members was crucial in obtaining the various state and Federal environmental permits. All project permitting team members participated in weekly meetings during application preparation. Discussions at these meetings ranged from recent public contacts, to application content, to environmental design considerations. Establishing a project manager was critical to the team's success. The project manager was responsible for seeing that permit acquisition, facility construction, and operation of the mining complex proceeded on schedule. The project manager had the final word, mediated disagreements, and frequently served as project spokesman to the public. Identifying red flag issues Red flag issues are those environmental factors with the most potential for delaying the schedule or stopping the project. The first red flag issue identified was organized local opposition. This opposition had completely derailed a US Soil Conservation Service proposal to build a multipurpose dam on Enlow Fork, a short distance
Citation
APA:
(1985) Permitting and compliance procedures outlined for Consol’s Bailey coal mineMLA: Permitting and compliance procedures outlined for Consol’s Bailey coal mine. Society for Mining, Metallurgy & Exploration, 1985.