PSEG Lawrenceburg Energy Facility Augered Cast -In-Place Piles Case History

Deep Foundations Institute
Chris D. Shewmaker
Organization:
Deep Foundations Institute
Pages:
11
File Size:
4476 KB
Publication Date:
Jan 1, 2004

Abstract

So you want to install 2,600 augered cast-in-place piles, about 155,000 lineal feet, in 33 working days? It can be done. The Public Service Enterprise Group (PSEG) decided to build a combined cycle power plant in Lawrenceburg, Indiana. PSEG selected Fluor Constructors Indiana, L.P. to design and build the plant. Fluor Constructors, in turn, selected Richard Goettle, Inc. to install the piles. The initial plan was to install the 2,600 piles in 33 days, working six (6) ten hour days per week. After successfully installing and performing four pile load tests - up to 300 ton capacity - we set out to complete the work and meet the aggressive schedule. After three weeks of installing an average of 75 piles a day with three drill rigs, Fluor relaxed the schedule because we were so far ahead of their projected construction sequence. We elected to continue drilling on a ten-hour day, five days a week schedule. In all, we installed nearly 2,800 piles, totaling 175,000 lineal feet, in about 47 days.
Citation

APA: Chris D. Shewmaker  (2004)  PSEG Lawrenceburg Energy Facility Augered Cast -In-Place Piles Case History

MLA: Chris D. Shewmaker PSEG Lawrenceburg Energy Facility Augered Cast -In-Place Piles Case History. Deep Foundations Institute, 2004.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account