Reconditioning the Howey Shaft

Canadian Institute of Mining, Metallurgy and Petroleum
R. R. Bassermann
Organization:
Canadian Institute of Mining, Metallurgy and Petroleum
Pages:
5
File Size:
1756 KB
Publication Date:
Jan 1, 1935

Abstract

THE property of Howey Gold Mines, Limited is situated at Red Lake, Ontario, one hundred and seventy-five miles east of Winnipeg and eighty miles north of the Canadian National Railway line. The mine has been a continuous producer since April, 1930, and at present is hoisting 1,350 tons of ore per day. The shaft consists of three compartments (see Figure 1, sketch B). Hoisting is done by two skips in balance, one of which is interchangeable with a cage. Sinking had been carried out at three different periods. From the surface to the 550-foot level, the sets had been spaced at seven-foot intervals, from the 550-to the 1,060-foot level at six feet, and from the 1,060-to the 1,500-foot level at five feet. During the five years of operation, the shaft had become so badly worn, due to spill from the tipples and, to a certain extent, from the loading pockets, that re-timbering was considered necessary. It should be explained that no crushing is done underground because of the ad verse effect this would have on the efficiency of the sorting. The grizzly rail clearance above the ore pockets is fourteen inches and consequently the ore hoisted is extremely coarse. More than average spill from the loading pockets and tipples under such conditions is inevitable, and it is debatable whether underground crushing with consequent increased sorting costs would not be justified. The cost of complete re-timbering according to standard practice would have been prohibitive both directly and indirectly: A lengthy shut-down of the shaft, with the consequent disorganization of the staff and workmen, could not be considered. Accordingly, it became necessary to devise some method of repair that could be carried to completion in a very limited period of time. The shaft timber for the first 250 feet was not in need of repair. From the 250-foot to the 1,060-foot level the wall plates, posts, and blocking were in good condition. These had been protected by a one-inch plank lining put in at various periods during the past three years without interfering with hoisting operations. The end plates and dividers, however, could not be protected in this manner because of the lack of skip clearance. It was decided that, if the dividers in this section could be replaced, the shaft would be as satisfactory as if completely re-timbered. Several factors had to be taken into consideration in deciding on a suit-able method of repair. In the first place, the tipple plates had to be re-designed. To complete the job in a reasonable time, not only had work to be done on the tipple, but simultaneously from several points in the shaft itself. Since all power cables, pipe lines, etc., were in the manway compartment of the shaft, this compartment had to be left undisturbed.
Citation

APA: R. R. Bassermann  (1935)  Reconditioning the Howey Shaft

MLA: R. R. Bassermann Reconditioning the Howey Shaft. Canadian Institute of Mining, Metallurgy and Petroleum, 1935.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account