Sandwich Wall Beneath Amsterdam Centraal Station - An Innovative Approach For Jet Grouting Under Difficult Conditions

Deep Foundations Institute
J. C. W. M. de Wit
Organization:
Deep Foundations Institute
Pages:
14
File Size:
1181 KB
Publication Date:
Jan 1, 2006

Abstract

An excavation, within which a tunnel is sunk as a part of the Centraal Station underground station (platform section) of the Noord/Zuidlijn ('North/South Line'), is to be created beneath the Amsterdam Centraal ('Amsterdam Central') station. The section beneath Amsterdam Centraal Station is characterised by the application of a particular technology in the form of, inter alia, the so-called 'sandwich wall'. This is a composite wall consisting of two rows of Tubex piles with a body of jetgrout columns in-between. This wall acts both as an excavation support wall and also provides vertical bearing. The installation of the wall, including both Tubex piles and jetgrout columns, within these specific conditions (limited height, sensitive historical building), within the design requirements set in terms of construction tolerance and water and soil retention, may be regarded as being a pioneering achievement. The environmental constraints are that the trains should continue to run, the inconvenience to passengers should be kept to a minimum and the historic station should not suffer any damage. Because of the complexity of the working conditions, the project is being overseen by a steering group of experts in the specified construction processes. In order to manage the project risks, jet grouting trials were initially carried out, in order to highlight and control execution problems; the practicability of the design is then tested. Work commenced on the sandwich wall in 2003, when the wooden piles were extracted at the locations where the sandwich wall was to be constructed; in 2004, the steel Tubex piles for the southern wall sections were installed. From May 2005, the construction of the sandwich wall got under way; in addition to the described process supervision, an extensive measuring programme was established, so that the process could be adjusted as necessary and the quality of the finished product determined. This applied to both individual columns and for the end product, the sandwich wall. The measurement results were processed for each column, interpreted and the effect on the work still to be conducted was assessed for each future column. Preventative and corrective measures were, if necessary, taken in order to control or counteract the measured defect. In addition to the process-oriented and qualitative measurements, various independent measurement systems at the station building served as a further control in order to prevent damage to the building.
Citation

APA: J. C. W. M. de Wit  (2006)  Sandwich Wall Beneath Amsterdam Centraal Station - An Innovative Approach For Jet Grouting Under Difficult Conditions

MLA: J. C. W. M. de Wit Sandwich Wall Beneath Amsterdam Centraal Station - An Innovative Approach For Jet Grouting Under Difficult Conditions. Deep Foundations Institute, 2006.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account