Scheduling Of Excavation For Underground Powerhouses

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 20
- File Size:
- 710 KB
- Publication Date:
- Jan 1, 1983
Abstract
In underground powerhouse excavations, the access to the horizontal sections of the penstocks is most often critical. Other factors which influence the schedule include: the sequences of excavation, the interface dates between contracts, the type of support for the overhead cranes and whether the roof in the powerhouse is a reinforced concrete arch or a suspended prefabricated material. At Outardes 3, Churchill Falls and LG-2, these factors, along with the size of the powerhouse and the local topgraphy and geology were studied to produce the optimum schedule.
Citation
APA:
(1983) Scheduling Of Excavation For Underground PowerhousesMLA: Scheduling Of Excavation For Underground Powerhouses. Society for Mining, Metallurgy & Exploration, 1983.