Sequential Excavation Method with Ground Freezing for DC Water’s First Street Tunnel

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 7
- File Size:
- 10498 KB
- Publication Date:
- Jan 3, 2018
Abstract
"DC Water’s First Street Tunnel (FST) is part of the $2.6 billion Clean Rivers Project designed to reduce the occurrence of combined sewer overflows into local waterways. Due to flood events in the Bloomingdale and LeDroit Park neighborhoods, the FST Project was accelerated by DC Water to mitigate future flooding by boosting storage capacity and thus relieving the undersized combined sewers.The FST Project was finalized in 2016 as a collaborative effort between DC Water, its consulting team consisting of Greeley & Hansen and McMillen Jacobs Associates, and the design-build team of Skanska, Jay Dee Contractors (SKJD) with WSP Parsons Brinckerhoff as the designer.Scope of project. The FST Project (Fig. 1) included four primary shaft sites, a large 6 m (20 ft) internal diameter, 823- m (2,700-ft) long bored tunnel and three adit connections from the off-line shafts to the large-diameter tunnel. The adits which vary in size and length, are the subject of this article. The Channing Street site (Fig. 2) was established as the main site for an Earth pressure balance tunnel boring machine (TBM) and included a 49-m (160-ft) deep shaft with slurry wall support of excavation and 20-m (65-ft) internal diameter final cast-in-place permanent concrete liner. The construction sites at Adams Street, V Street and Thomas Street each consisted of off-line shaft structures tied to near-surface sewer diversion chambers and ventilation facilities. These three off-line shafts were connected to the large bored TBM tunnel via adit tunnels. Each of the three adits had a portion or the entire length excavated by sequential excavation method (SEM) in frozen ground.The Adams Street adit (Fig. 3) was constructed in two phases. The first phase is the 23-m (75-ft) long and 5-m (16-ft) diameter section immediately outside the drop shaft which also serves as the deaeration chamber and was excavated by SEM. The second phase which is 91 m (300 ft) long and 3 m (10 ft) in diameter was excavated by Micro TBM (MTBM) launched from within the permanently lined deaeration chamber. MTBM excavation commenced toward a reception chamber that was excavated by SEM from the previously bored FST TBM tunnel. This SEM excavation had a 5 m (17 ft) diameter and a length of 4.5 m (15 ft)"
Citation
APA:
(2018) Sequential Excavation Method with Ground Freezing for DC Water’s First Street TunnelMLA: Sequential Excavation Method with Ground Freezing for DC Water’s First Street Tunnel. Society for Mining, Metallurgy & Exploration, 2018.