Shaft Construction in Toronto Using Slurry Walls

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 5
- File Size:
- 200 KB
- Publication Date:
- Jan 1, 2007
Abstract
PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located just north of Toronto, Ontario, Canada will see the construction of a tunnel extending along 19th Avenue for a length of approximately 3.8 Km from Yonge Street, east to Leslie Street and will have a minimum internal diameter of 2.1 m. t to Leslie Street and will have a minimum internal diameter of 2.1 m. The tunnel will connect into four shafts, for which two of the shafts will be constructed using the slurry wall construction method given the high water table and difficult ground conditions encountered at these locations. The two shafts noted as Access Shaft No. 2 and No. 3 were designed and constructed to meet regulatory conditions, which required a sealed shaft construction method. GEOGRAPHICAL PROFILE The ground conditions in the Toronto region consist predominately of glacial till, glaciolacustrine and glaciofluvial sand, silt and clay deposits, and beach sands and gravels. The shallow geological formation found in the project area consists of four types of deposits: Oak Ridge Morain deposits, Halton Till, Glacial lake deposits and Organic soils. The Oak Ridge Morain is the dominant deposit encountered along the tunnel alignment. This formation consists of three deposits: The Upper Till, Middle Sand and the Lower Till. Standard penetration tests (SPT) carried out in these deposits measured N-values ranging from 2 to more than 100 blows/300mm which indicate very loose to very dense soil conditions. The Middle Sand deposit will be the dominant feature within the slurry wall construction at access shafts 2 and 3. Access Shaft 3 The base of the slurry wall will be 20.5 M below the ground surface. Slurry wall excavation will be within peat and organic soils found at the upper 3 M, followed by 5 M of the Upper Till. The remainder of the excavation will be within the Middle Sand. The piezometric head elevation is found at the ground surface. Access Shaft 2 The base of the slurry wall will be 22.5 M below the ground surface. Slurry wall excavation will be entirely within the Middle Sand 2.The piezometric head elevation is found at 7 M below the ground surface.
Citation
APA:
(2007) Shaft Construction in Toronto Using Slurry WallsMLA: Shaft Construction in Toronto Using Slurry Walls. Society for Mining, Metallurgy & Exploration, 2007.