Shallow Microtunneling below a Critical Runway

Society for Mining, Metallurgy & Exploration
Matthew Grzelak David R. Chapman Gulsah Erinc
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
11
File Size:
879 KB
Publication Date:
Jan 1, 2016

Abstract

"The third phase of the Bagram Drainage System project at Bagram Air Force Base in Afghanistan included construction of a shallow, 540-m long, 1.8-m inside diameter drainage tunnel. The tunnel penetrated mostly stiff to hard clayey and silty soils. The contractor’s Value Engineering Change Proposal (VECP) to use pipe-jacking with a microtunnel boring machine (MTBM) instead of the specified two-pass Earth Pressure Balance method was evaluated and supported using hand calculations. Contractor support was provided throughout the project by providing design reviews and instrumentation monitoring during construction. This paper compares the value-engineering proposal to the specified method and describes the construction conditions encountered. INTRODUCTION As part of a larger improvement project at the Bagram Air Force Base in Afghanistan, a shallow, 540-m long, 1.8-m inside diameter drainage tunnel was constructed to provide additional capacity for Coyote Creek to pass below several critical structures, including taxiways and the main runway, for mitigation of recurring flooding (see Figures 1 and 2). Overburden over the tunnel crown ranged from about 3 m to 5.5 m. An existing cast-in-place twin barrel concrete culvert runs approximately parallel to the new tunnel and is within about 8 m at its closest point. The contractor’s Value Engineering Change Proposal (VECP) to the specified two-pass Earth Pressure Balance (EPB) method (steel ribs and lagging or steel liner plate with a carrier pipe later grouted in-place) called for installation of the required drainage pipe by pipe-jacking (one-pass installation) using a slurry microtunnel boring machine (MTBM). The critical nature of the operations at the air base resulted in significant construction coordination challenges and a greater than usual need to avoid excessive settlements. Substantial restrictions were placed on drilling of investigative borings and installing instrumentation near runways and taxiways due to drill mast height. The prime contractor was SERKA TAAHHUT INSAAT A. S. (SERKA), the microtunneling subcontractor was Ludwig Pfeiffer Microtunnel GmbH & Co.KG (Pfeiffer), the jacking pipe designer was Gollwitzer Pipe and Shaft Technology GmbH (Gollwitzer), and the contractor’s tunnel engineer was Lachel & Associates, Inc. (Lachel). Lachel provided contractor support throughout the project including preparation of a VECP/Design Summary (including interpretation of existing and new geotechnical information), design reviews for jacking pipe, estimating settlement of an existing drainage structure above the new tunnel, and instrumentation planning, monitoring, and analysis during construction."
Citation

APA: Matthew Grzelak David R. Chapman Gulsah Erinc  (2016)  Shallow Microtunneling below a Critical Runway

MLA: Matthew Grzelak David R. Chapman Gulsah Erinc Shallow Microtunneling below a Critical Runway. Society for Mining, Metallurgy & Exploration, 2016.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account