Summersville Raw Water Intake

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 11
- File Size:
- 4438 KB
- Publication Date:
- Jan 1, 2005
Abstract
Construction for the new 2.5 MGPD raw water intake project commenced December 2002. The project, initially designed as a 12' Ø concrete lined intake shaft,145' deep, with two offset 24" lake taps, 520' and 470' long was subsequently “value engineered” running the two lake taps through a single conduit. The offset for summer and winter pools was accomplished via a second shaft located at the lakes edge. Construction involved the use of blind drilling techniques for the shaft development and drill and blast techniques for the tunneling. All works were completed through extremely hard crystallized sandstone. The project came online August 12, 2004.